Permit: T19CM05619
Permit Details
Apply Date:
08/06/2019
Applicant:
SUNSET WEST CONSTRUCTION LLC
Description:
NEW SFR SWC1320 T19-M0080
Contractors:
- SUNSET WEST CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM05619
Permit Status: C of o
Permit Description: NEW SFR SWC1320 T19-M0080
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 08/06/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM05619
Permit Status: C of o
Permit Description: NEW SFR SWC1320 T19-M0080
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/06/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM05619
Permit Description: NEW SFR SWC1320 T19-M0080
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/13/2019 | PLUMBING - YARD WTR LINE/TEST | AKLEINSORGE | Approved | Ok to backfill |
| 08/13/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | Ok to backfill |
| 08/14/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 08/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 08/27/2019 | ROOF NAILING | MHASSAN | Approved | |
| 08/27/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
| 08/30/2019 | FRAMING | BSTEVENS | Approved | |
| 08/30/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | complete blocking on supplies in bathrooms |
| 08/30/2019 | RESIDENTIAL INTERMEDIATE | MHASSAN | Approved | |
| 09/09/2019 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
| 09/09/2019 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is ECO. |
| 09/09/2019 | ELECTRIC - UFER | ESTEVENS | Approved | |
| 12/23/2019 | MECHANICAL - FINAL | WGALLAGHER | Approved | Condensate not installed properly |
| 12/23/2019 | PLUMBING - SEWER HCS CONNECT | WGALLAGHER | Approved | Denied not ready |
| 12/23/2019 | PLUMBING - INTERMEDIATE | WGALLAGHER | Approved | Denied not ready |
| 12/23/2019 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Denied not ready |
| 12/23/2019 | ELECTRIC - FINAL | WGALLAGHER | Approved | Denied not ready |
| 12/23/2019 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | |
| 12/23/2019 | BUILDING - FINAL | WGALLAGHER | Approved | Denied not ready |
| 01/22/2020 | PLUMBING - FINAL | BSTEVENS | Approved | RVI |
| 01/22/2020 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved |