Permit: T19CM05232
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
6188 E PIMA ST BLDG 1
Address NEW:
6188 E PIMA ST BLDG 1
Apply Date:
07/24/2019
Applicant:
N/A
Description:
TI & ADDITION SCHOOL
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM05232
Permit Status: C of o
Permit Description: TI & ADDITION SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/24/2019 | PLANS OK TO SUBMIT - COMM | 08/12/2019 | COMPLETED |
| 08/12/2019 | COMMERCIAL - TI | 10/02/2019 | COMPLETED |
| 10/02/2019 | RESUBMITTAL - TI ALL | 11/04/2019 | COMPLETED |
| 11/04/2019 | RESUBMITTAL | 11/07/2019 | COMPLETED |
| 11/27/2019 | REVISION - - 1ST | 12/05/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM05232
Permit Status: C of o
Permit Description: TI & ADDITION SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/24/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM05232
Permit Description: TI & ADDITION SCHOOL
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/08/2019 | SITE - SEWER | RCHANDLER | Approved | |
| 11/08/2019 | ELECTRIC - TEMPORARY SERVICE | RCHANDLER | Approved | |
| 11/08/2019 | ELECTRIC - UFER | RCHANDLER | Approved | |
| 11/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 11/15/2019 | STEM WALL/RETAINING WALL | DQUINN | Approved | 2 hour stem ok to grout. Bldg 1 platform ramp footings ok to pour. |
| 12/02/2019 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | ALL ROUGH PLUMBING WAS APPROVED BY RCHANDLER ON 12/02/2019 |
| 12/02/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | Addition only. |
| 12/03/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | |
| 12/05/2019 | PLUMBING - PROGRESS | MRAMBER | Approved | Plumbing rough at building a admin ok. |
| 12/06/2019 | PLUMBING - PRE SLAB | MRAMBER | Approved | |
| 12/06/2019 | BUILDING PRE-SLAB | MRAMBER | Approved | |
| 12/12/2019 | BUILDING - PROGRESS | RCHANDLER | Approved | SES slab and two ramps. |
| 12/16/2019 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | North parking lot, light poles, conduit ok. |
| 01/29/2020 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | |
| 03/24/2020 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 04/08/2020 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | RVI |
| 04/08/2020 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | RVI |
| 04/08/2020 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | RVI |
| 04/08/2020 | FRAMING | RCHALLANGER | Approved | RVI |
| 04/10/2020 | ROOF NAILING | RCHANDLER | Approved | Inspected via email. |
| 04/16/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
| 04/28/2020 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE ECO |
| 04/28/2020 | ELECTRIC - SERVICE UPGRADE | WGALLAGHER | Approved | ok for clearance ECO TEPCalled at 10:54 |
| 06/09/2020 | MECHANICAL - ABOVE CEILING | TTREMBULAK | Approved | |
| 06/09/2020 | PLUMBING - ABOVE CEILING | TTREMBULAK | Approved | |
| 06/09/2020 | ELECTRIC - ABOVE CEILING | TTREMBULAK | Approved | |
| 06/09/2020 | BUILDING ABOVE CEILING | TTREMBULAK | Approved | Approved. Will leave ceiling open for roof drain inspection (A131,A132,A124,A125) |
| 07/09/2020 | PLUMBING - ROOF DRAINS | TTREMBULAK | Approved | Approved |
| 07/17/2020 | MECHANICAL - PROGRESS | TTREMBULAK | Approved | Approved |
| 07/17/2020 | MECHANICAL - FINAL | TTREMBULAK | Approved | Approved |
| 07/17/2020 | ELECTRIC - FINAL | TTREMBULAK | Approved | Approved |
| 07/22/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | Approved |
| 07/22/2020 | U VALUE FOR WINDOW | WGALLAGHER | Approved | Approved |
| 07/22/2020 | NPPO - FINAL | DROBERTS | Approved | IS APPROVED |
| 07/22/2020 | SIGN - FINAL | DROBERTS | Approved | IS APPROVED |
| 07/27/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | Approved |
| 07/27/2020 | LANDSCAPE - FINAL | RLEDONNE | Approved | Approved. |
| 08/03/2020 | RIGHT OF WAY - FINAL | MVV | Approved | Acceptable. |
| 08/05/2020 | PLUMBING - FINAL | WGALLAGHER | Approved | approved |
| 08/11/2020 | FIRE - FINAL | MRoss | Approved | |
| 08/12/2020 | ENGINEERING - FINAL | RLEDONNE | Approved | Approved. |
| 08/14/2020 | BUILDING - FINAL | WGALLAGHER | Approved | Approved recommended for C/O |
| 08/14/2020 | BUILDING - FINAL | JG3 | Approved | |
| 08/14/2020 | HEALTH DEPT - FINAL 724-7908 | JG3 | Approved |