Permit: T19CM04663
Permit Details
Apply Date:
06/28/2019
Applicant:
N/A
Description:
REMODEL SFR: ADD BEDROOM, BATHROOM, AND REAR PORCH
Permit Reviews
Permit Number - T19CM04663
Permit Status: Final
Permit Description: REMODEL SFR: ADD BEDROOM, BATHROOM, AND REAR PORCH
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/29/2020 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 06/11/2020 | COMPLETED |
06/11/2020 | RESUBMITTAL | 06/19/2020 | COMPLETED |
06/28/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 05/08/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04663
Permit Status: Final
Permit Description: REMODEL SFR: ADD BEDROOM, BATHROOM, AND REAR PORCH
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/28/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM04663
Permit Description: REMODEL SFR: ADD BEDROOM, BATHROOM, AND REAR PORCH
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/04/2020 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Approved. Continuous footing for addition; column footings in interior of structure . Ok to place concrete in progress areas. |
08/05/2020 | STEM WALL/RETAINING WALL | TVALENCIA | Approved | approved |
08/06/2020 | ELECTRIC - UNDERGROUND | TTREMBULAK | Approved | Approved |
08/06/2020 | PLUMBING - ROUGH, SOIL | TTREMBULAK | Approved | Approved |
08/06/2020 | BUILDING PRE-SLAB | TTREMBULAK | Approved | Approved |
09/22/2020 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | Both are approved |
09/22/2020 | ROOF NAILING | ESTEVENS | Approved | Both are approved |
09/25/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Not ready, not complete. |
09/25/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | Not ready, not complete. |
09/25/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | All four are approved. |
09/25/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | All four are approved. |
09/25/2020 | RESIDENTIAL INTERMEDIATE | ESTEVENS | Approved | All four are approved. |
09/25/2020 | FRAMING | ESTEVENS | Approved | All four are approved. |
11/20/2020 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | Approved. Ok to cover progress areas. |
12/31/2020 | PLUMBING - FINAL | ESTEVENS | Approved | Denied. No messages, no contractor listed. Please call your inspector for further information to set up a video inspection. |
12/31/2020 | BUILDING - FINAL | ESTEVENS | Approved | Denied. No messages, no contractor listed. Please call your inspector for further information to set up a video inspection. |
01/05/2021 | GAS CLEARANCE | JBURGE | Approved | CODE |
01/05/2021 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | APPROVED |