Permit: T19CM04593
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
6894 E VIA RANCHO ROSARIO
Address NEW:
6894 E VIA RANCHO ROSARIO
Apply Date:
06/26/2019
Applicant:
MERITAGE HOMES CONSTRUCTION INC *** APA***
Description:
SFR 2302380 T19-M0053
Contractors:
- MERITAGE HOMES CONSTRUCTION INC *** APA***
Outstanding Activity Conditions
Permit Number - T19CM04593
Permit Status: Final
Permit Description: SFR 2302380 T19-M0053
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/26/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM04593
Permit Description: SFR 2302380 T19-M0053
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/28/2019 | PLUMBING - FINAL | GKOL | Approved | P19WX01482 - SWR_LA ESTANCIA DE TUCSON LOT 589 SFR - ISSUED WITH PCRWRD CONDITIONS: NO PHYSICAL CONNECTION TO THE PUBLIC SEWER SYSTEM UNTIL THE PUBLIC SEWER G-2017-078 IS ACCEPTED AND RELEASED BY PCRWRD - NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PUBLIC SEWER G-2017-078 IS ACCEPTED AND RELEASED BY PCRWRD |
| 07/19/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
| 07/19/2019 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | |
| 07/19/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
| 07/29/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | |
| 07/29/2019 | ELECTRIC - UFER | AKLEINSORGE | Approved | |
| 07/29/2019 | BUILDING PRE-SLAB | AKLEINSORGE | Approved | Ok for concrete placement |
| 07/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | Move #4 rebar to go around plumbing box, ok for concrete placement |
| 08/21/2019 | ROOF NAILING | AKLEINSORGE | Approved | |
| 08/21/2019 | EXT METAL CLIPS/EXT SHEATHING | AKLEINSORGE | Approved | |
| 09/03/2019 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
| 09/03/2019 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Clear TEP (ECO). |
| 09/17/2019 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | Clear Southwest Gas. |
| 09/17/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 09/17/2019 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
| 09/17/2019 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
| 09/17/2019 | FRAMING | DMUNIZ | Approved | |
| 10/03/2019 | SHEET ROCK NAILING | BSTEVENS | Approved | (RVI) |
| 11/05/2019 | GAS CLEARANCE | BSTEVENS | Approved | RESEND |
| 11/18/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 11/18/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 11/18/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 12/11/2019 | BUILDING - FINAL | DMERANZ1 | Approved | ALL DOCUMENTS TURNED IN AND APPROVED THANK YOU |