Permit: T19CM04512
Permit Details
Apply Date:
06/25/2019
Applicant:
VENEZIANO, PHILIP JOHN
Description:
TI: WAREHOUSE (BUILDING B)
Architects:
- VENEZIANO, PHILIP JOHN
Contractors:
- WENTZ AND PATRICK CONSTRUCTION C
Permit Reviews
Permit Number - T19CM04512
Permit Status: L of c
Permit Description: TI: WAREHOUSE (BUILDING B)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/25/2019 | COMMERCIAL - TI | 08/16/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04512
Permit Status: L of c
Permit Description: TI: WAREHOUSE (BUILDING B)
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/25/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM04512
Permit Description: TI: WAREHOUSE (BUILDING B)
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2019 | PLUMBING - ROUGH, SOIL | JCLAXTON | Approved | Ok to bury. |
| 11/29/2019 | FRAMING | JCLAXTON | Approved | |
| 11/29/2019 | PLUMBING - INTERMEDIATE | JCLAXTON | Approved | Bathrooms and mop sink. Ok to proceed |
| 11/29/2019 | ELECTRIC - INTERMEDIATE | JCLAXTON | Approved | Walls only. |
| 12/03/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 12/11/2019 | SHEET ROCK NAILING | ESTEVENS | Approved | |
| 01/13/2020 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | Clear ECO/RECN for panels servicing - Suite 100 and 200 |
| 01/13/2020 | TEP CLEARANCE - PM | DQUINN | Approved | panels servicing - Suite 100 and 200 CODE ECO/RECN |
| 01/13/2020 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | Note: electric clearance inspection was not on gutted warehouse permits. |
| 01/13/2020 | PLUMBING - FINAL | DQUINN | Approved | |
| 01/21/2020 | FIRE - FINAL | gsereno1 | Approved | |
| 01/21/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
| 01/21/2020 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | |
| 01/21/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | |
| 03/06/2020 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 03/11/2020 | BUILDING - FINAL | ESTEVENS | Approved | |
| 03/11/2020 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |