Permit: T19CM04414
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
2861 W CALLE GARDENIAS
Address NEW:
2861 W CALLE GARDENIAS
Apply Date:
06/20/2019
Applicant:
TATE WYLY, P.E.
Description:
ADD MASTERSUITE AND OFFICE
Contractors:
- WYCO ENGINEERING AND CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM04414
Permit Status: Final
Permit Description: ADD MASTERSUITE AND OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/20/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 06/20/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04414
Permit Status: Final
Permit Description: ADD MASTERSUITE AND OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/20/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM04414
Permit Description: ADD MASTERSUITE AND OFFICE
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 07/26/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
| 07/26/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 07/26/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | 1- Shall provide the approved plans on site at the time of inspection request. |
| 07/26/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 09/04/2019 | ROOF NAILING | DQUINN | Approved | |
| 09/04/2019 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 10/10/2019 | FRAMING | TVALENCIA | Approved | |
| 10/18/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 01/09/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 01/09/2020 | PLUMBING - FINAL | DQUINN | Approved | |
| 01/09/2020 | MECHANICAL - FINAL | DQUINN | Approved | |
| 02/12/2020 | BUILDING - FINAL | TVALENCIA | Approved | |
| 02/12/2020 | ELECTRIC - FINAL | TVALENCIA | Approved |