Permit: T19CM04396
Permit Details
Apply Date:
06/19/2019
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR PLAN400218 T18-M0087
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC
Permit Reviews
Permit Number - T19CM04396
Permit Status: Final
Permit Description: SFR PLAN400218 T18-M0087
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/19/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 06/20/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04396
Permit Status: Final
Permit Description: SFR PLAN400218 T18-M0087
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/19/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM04396
Permit Description: SFR PLAN400218 T18-M0087
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/25/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | Ok to backfill |
07/25/2019 | PLUMBING - YARD WTR LINE/TEST | AKLEINSORGE | Approved | Ok to backfill |
07/25/2019 | PLUMBING - SEWER HCS CONNECT | AKLEINSORGE | Approved | Ok to backfill |
07/25/2019 | PLUMBING - BACK WATER VALVE | AKLEINSORGE | Approved | Ok to backfill |
07/30/2019 | ELECTRIC - UFER | AKLEINSORGE | Approved | |
07/30/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | |
07/30/2019 | BUILDING PRE-SLAB | AKLEINSORGE | Approved | Ok for concrete placement |
07/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | Ok for concrete placement |
08/15/2019 | ROOF NAILING | MHASSAN | Approved | fix trusses at back of house as they only have one middle bearing point being the exterior patio wall, not the interior bedroom wall. Please provide room for deflection at that wall. |
08/15/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
10/01/2019 | TEP CLEARANCE - PM | BSTEVENS | Approved | CODE ECO |
10/01/2019 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | (RVI) |
10/11/2019 | GAS CLEARANCE | JCLAXTON | Approved | |
10/11/2019 | PLUMBING - GAS PRESSURE TEST | JCLAXTON | Approved | Clear SWG. |
10/11/2019 | MECHANICAL - INTERMEDIATE | JCLAXTON | Approved | |
10/11/2019 | PLUMBING - INTERMEDIATE | JCLAXTON | Approved | |
10/11/2019 | FRAMING | JCLAXTON | Approved | |
10/21/2019 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
01/13/2020 | PLUMBING - PROGRESS | DMUNIZ | Approved | |
01/13/2020 | PLUMBING - PROGRESS | DMUNIZ | Approved | |
01/13/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
01/13/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
01/13/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
01/13/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
10/18/2022 | BUILDING - FINAL | CTREVIL | Approved |