Permit: T19CM04089
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
2333 E GLENN ST 101
Address NEW:
2333 E GLENN ST 101
Apply Date:
06/07/2019
Applicant:
Javier Arvizu
Description:
repl furnace/cooler w/heat pumps UNITS 101-123 1ST FLOOR 201-223 2ND FLOOR
Permit Reviews
Permit Number - T19CM04089
Permit Status: Issued
Permit Description: repl furnace/cooler w/heat pumps UNITS 101-123 1ST FLOOR 201-223 2ND FLOOR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/07/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/07/2019 | COMPLETED |
| 06/07/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/12/2019 | COMPLETED |
| 08/09/2019 | OTHER | 08/09/2019 | ACTIVE |
| 08/09/2019 | RESUBMITTAL | 08/09/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM04089
Permit Status: Issued
Permit Description: repl furnace/cooler w/heat pumps UNITS 101-123 1ST FLOOR 201-223 2ND FLOOR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/07/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T19CM04089
Permite Description: repl furnace/cooler w/heat pumps UNITS 101-123 1ST FLOOR 201-223 2ND FLOOR
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T19CM04089
Permit Description: repl furnace/cooler w/heat pumps UNITS 101-123 1ST FLOOR 201-223 2ND FLOOR
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/25/2019 | COT - LCEL - Electrical Underground | Passed | {Activity date: 10/25/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - All secondaries and feeders ok to backfill on north side of building. } |
|
| 10/25/2019 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 10/25/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - All secondaries and feeders ok to backfill on north side of building. } |
|
| 01/29/2020 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 01/29/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - } ; {Activity date: 11/04/2019; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - Units 222, 122, 220, 120, 218, 118, 216, 116, 214, 114, 212, 112, 210.} ; {Activity date: 10/09/2019; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by DMERANZ1 - 120 and 219 new feeder to stove through ceiling ok to patch. Ok to patch back all new stove feeders in occupied.} |
|
| 01/29/2020 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 01/29/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - SERVICE 1 FOR UNITS 115,117,119,121,123,215,217,219,221,223 SERVICE 3 FOR UNITS 107,109,111,113,207,209,211,213,HOUESE PANEL SERVICE 4A FOR UNITS 114,116,118,120,122,214,216,218,220,222 SERVICE 4B FOR UNITS 108,110,112,208,210,212 CODE INCR} |
|
| 01/29/2020 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 01/29/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DMERANZ1 - } ; {Activity date: 11/04/2019; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by DMERANZ1 - Units 222, 122, 220, 120, 218, 118, 216, 116, 214, 114, 212, 112, 210.} ; {Activity date: 10/09/2019; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by DMERANZ1 - 120 and 219 new feeder to stove through ceiling ok to patch. Ok to patch back all new stove feeders in occupied.} |
|
| 01/29/2020 | COT - LCEL - Service Upgrade | Passed | {Activity date: 01/29/2020; Status: Approved; Inspector: DQUINN; Comment: Entered by DQUINN1 - } | |
| 10/20/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: CTREVIL; Comment: Entered by CTREVIL1 - } ; {Activity date: 04/03/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VFLORES1 - Units 108 thru 123 and units 208 thru 223. Are complete.} |