Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T19CM03981
Permit Details
Apply Date:
06/05/2019
Applicant:
RYAN REPUCCI
Description:
SPLIT 4 BEDROOM EXST INTO 1 BEDROOM/2BEDROOM
Contractors:
- TOFEL CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM03981
Permit Status: C of o
Permit Description: SPLIT 4 BEDROOM EXST INTO 1 BEDROOM/2BEDROOM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/11/2020 | REVISION - - 1ST | 04/08/2020 | COMPLETED |
05/22/2020 | REVISION - - 2ND | 05/26/2020 | ACTIVE |
06/05/2019 | PLANS OK TO SUBMIT - COMM | 06/07/2019 | COMPLETED |
06/05/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/14/2019 | COMPLETED |
06/05/2019 | COMMERCIAL - TI | 07/10/2019 | COMPLETED |
06/12/2020 | REVISION - - 3RD | 06/12/2020 | ACTIVE |
07/10/2019 | RESUBMITTAL | 09/04/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03981
Permit Status: C of o
Permit Description: SPLIT 4 BEDROOM EXST INTO 1 BEDROOM/2BEDROOM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/05/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM03981
Permit Description: SPLIT 4 BEDROOM EXST INTO 1 BEDROOM/2BEDROOM
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/11/2019 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
06/12/2020 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
10/07/2020 | SHEET ROCK NAILING | DQUINN | Approved | For bldg. 10 - units 116, 216, 118, 218 |
10/12/2020 | TEP CLEARANCE - PM | DQUINN | Approved | CODE INCR For Building # 10, unit #s 112, 116, 118, 216, 218, 212, 122, 222 |
10/12/2020 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | Clear incr For Building # 10, unit #s 112, 116, 118, 216, 218, 212, 122, 222 All unit sub panels ok. |
10/26/2020 | FIREWALL/FIREBARRIER/FIRESTOP | ESTEVENS | Approved | All seven are approved. |
10/26/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | All seven are approved. |
10/26/2020 | FRAMING | ESTEVENS | Approved | All seven are approved. |
10/26/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | All seven are approved. |
10/26/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | All seven are approved. |
10/26/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | All seven are approved. |
10/26/2020 | FRAMING | ESTEVENS | Approved | All seven are approved. |
01/25/2021 | MECHANICAL - FINAL | RBOOHER | Approved | APPROVED UNITS 10110, 10210, 10112, 10212 |
01/26/2021 | ELECTRIC - UNDERGROUND | DQUINN | Approved | APPROVED |
01/26/2021 | ELECTRIC - UFER | DQUINN | Approved | APPROVED |
01/26/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | APPROVED |
01/26/2021 | ELECTRIC - FINAL | DQUINN | Approved | APPROVED ALL UNITS IN BUILDING 10 OK |
01/26/2021 | BUILDING - FINAL | DQUINN | Approved | APPROVED ALL UNITS IN BUILDING 10 OK |
02/02/2021 | ENGINEERING - FINAL | BBENEDON | Approved | Approved. Geoff with Tofel dent. All contracted work has been completed. Management is providing ground coverings. Geoff was informed that all ground coverings and cleanup shall be required for final approval of building five at the end of the month. |
02/02/2021 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | APPROVED |
02/03/2021 | FIRE - FINAL | wmotto | Approved | |
02/03/2021 | FIRE INTERMEDIATE | wmotto | Approved | |
02/03/2021 | FIRE - ALARM FINAL | wmotto | Approved | |
02/03/2021 | FIRE SPKLR - FINAL | wmotto | Approved |