Permit: T19CM03884
Permit Details
Apply Date:
05/31/2019
Applicant:
BARRIOS FRANCISCO M & MARIA ELVA CP/RS
Description:
NEW DUPLEX-3BEDROOM/2BATH
Permit Reviews
Permit Number - T19CM03884
Permit Status: Final
Permit Description: NEW DUPLEX-3BEDROOM/2BATH
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/31/2019 | PLANS OK TO SUBMIT - RES | 06/21/2019 | COMPLETED |
| 07/24/2019 | RESUBMITTAL | 08/02/2019 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T19CM03884
Permit Status: Final
Permit Description: NEW DUPLEX-3BEDROOM/2BATH
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/31/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM03884
Permit Description: NEW DUPLEX-3BEDROOM/2BATH
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/02/2019 | ROOF NAILING | KEN | Approved | ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION |
| 01/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 02/13/2020 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | |
| 03/02/2020 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | |
| 03/02/2020 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 04/01/2020 | PLUMBING - PRE SLAB | TVALENCIA | Approved | |
| 04/01/2020 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
| 04/29/2020 | REINFORCED MASONRY PRE-GROUT | TVALENCIA | Approved | |
| 08/12/2020 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE/#1 AND #2/ECO |
| 08/12/2020 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | approved |
| 08/12/2020 | PLUMBING - GAS PRESSURE TEST | TVALENCIA | Approved | approved |
| 08/12/2020 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | approved |
| 08/12/2020 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | approved |
| 08/12/2020 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | approved Clear electric ECO Unit 1, Unit. 2 |
| 08/12/2020 | FRAMING | TVALENCIA | Approved | approved |
| 10/30/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 10/30/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
| 10/30/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 10/30/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 10/30/2020 | ELECTRIC - UFER | DMUNIZ | Approved | |
| 11/02/2020 | GAS CLEARANCE | DMUNIZ | Approved | CODE |
| 11/02/2020 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | Approved clear Southwest Gas |
| 11/02/2020 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Approved |
| 12/17/2020 | BUILDING - FINAL | DMUNIZ | Approved | ENGINEERING FINALED. INSPECTOR ALREADY AP FINAL. |
| 12/17/2020 | ENGINEERING - FINAL | DROBERTS | Approved | IS APPROVED |