Permit Details

Status:
Final
Type:
DUPLEX NEW
Address:
4820 S 7TH AV #1
Address NEW:
4820 S 7TH AV #1
Apply Date:
05/31/2019
Applicant:
BARRIOS FRANCISCO M & MARIA ELVA CP/RS
Description:
NEW DUPLEX-3BEDROOM/2BATH

Permit Reviews

Permit Number - T19CM03884
Permit Status: Final
Permit Description: NEW DUPLEX-3BEDROOM/2BATH
Start Date Submittal Complete Date Status  
05/31/2019 PLANS OK TO SUBMIT - RES 06/21/2019 COMPLETED Review Details
07/24/2019 RESUBMITTAL 08/02/2019 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T19CM03884
Permit Status: Final
Permit Description: NEW DUPLEX-3BEDROOM/2BATH
Total Outstanding Activity Conditions - 1
Date Name
05/31/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T19CM03884
Permit Description: NEW DUPLEX-3BEDROOM/2BATH
Total Completed Inspections - 25
Date Description Inspector Results Comments
08/02/2019 ROOF NAILING KEN Approved ROOF TRUSSES MUST BE APPROVED PRIOR TO INSPECTION
01/30/2020 EXCAVATION/LAYOUT REBAR & ZON TVALENCIA Approved
02/13/2020 STEM WALL/RETAINING WALL RCHANDLER Approved
03/02/2020 PLUMBING - SEWER HCS CONNECT TVALENCIA Approved
03/02/2020 PLUMBING - ROUGH, SOIL TVALENCIA Approved
04/01/2020 PLUMBING - PRE SLAB TVALENCIA Approved
04/01/2020 BUILDING PRE-SLAB TVALENCIA Approved
04/29/2020 REINFORCED MASONRY PRE-GROUT TVALENCIA Approved
08/12/2020 TEP CLEARANCE - PM TVALENCIA Approved CODE/#1 AND #2/ECO
08/12/2020 MECHANICAL - INTERMEDIATE TVALENCIA Approved approved
08/12/2020 PLUMBING - GAS PRESSURE TEST TVALENCIA Approved approved
08/12/2020 PLUMBING - YARD WTR LINE/TEST TVALENCIA Approved approved
08/12/2020 PLUMBING - INTERMEDIATE TVALENCIA Approved approved
08/12/2020 ELECTRIC - CONSTRUCTION POWER TVALENCIA Approved approved
Clear electric ECO Unit 1, Unit. 2
08/12/2020 FRAMING TVALENCIA Approved approved
10/30/2020 MECHANICAL - FINAL DMUNIZ Approved
10/30/2020 PLUMBING - FINAL DMUNIZ Approved
10/30/2020 OUTDOOR LIGHTING FINAL DMUNIZ Approved
10/30/2020 ELECTRIC - FINAL DMUNIZ Approved
10/30/2020 ELECTRIC - UFER DMUNIZ Approved
11/02/2020 GAS CLEARANCE DMUNIZ Approved CODE
11/02/2020 RESIDENTIAL INTERMEDIATE DMUNIZ Approved Approved clear Southwest Gas
11/02/2020 ELECTRIC - UNDERGROUND DMUNIZ Approved Approved
12/17/2020 BUILDING - FINAL DMUNIZ Approved ENGINEERING FINALED. INSPECTOR ALREADY AP FINAL.
12/17/2020 ENGINEERING - FINAL DROBERTS Approved IS APPROVED

Documents

File Name Document Type  
001_1 OF 8.TIF CONSTRPLANS VIEW
002_2 OF 8.TIF CONSTRPLANS VIEW
003_3 OF 8.TIF CONSTRPLANS VIEW
004_4 OF 8.TIF CONSTRPLANS VIEW
005_5 OF 8.TIF CONSTRPLANS VIEW
006_6 OF 8.TIF CONSTRPLANS VIEW
007_7 OF 8.TIF CONSTRPLANS VIEW
008_8 OF 8.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW