Permit Details

Status:
Final
Type:
SINGLE FAMILY NEW
Apply Date:
05/21/2019
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR DRHT308018 T18-M0052
Contractors:
  • D R H TUCSON CONSTRUCTION

Permit Reviews

Permit Number - T19CM03601
Permit Status: Final
Permit Description: SFR DRHT308018 T18-M0052
Start Date Submittal Complete Date Status  
05/21/2019 RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU 05/21/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM03601
Permit Status: Final
Permit Description: SFR DRHT308018 T18-M0052
Total Outstanding Activity Conditions - 1
Date Name
05/21/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T19CM03601
Permit Description: SFR DRHT308018 T18-M0052
Total Completed Inspections - 24
Date Description Inspector Results Comments
06/04/2019 PLUMBING - SEWER HCS CONNECT MHASSAN Approved
06/04/2019 PLUMBING - ROUGH, SOIL MHASSAN Approved fix downstairs bath, piping missing P-trap.
06/13/2019 BUILDING PRE-SLAB RCAMACHO Approved
06/13/2019 EXCAVATION/LAYOUT REBAR & ZON RCAMACHO Approved
06/19/2019 ELECTRIC - UFER RCAMACHO Approved
06/19/2019 ELECTRIC - CONSTRUCTION POWER RCAMACHO Approved ECO
06/19/2019 TEP CLEARANCE - PM RCAMACHO Approved CODE ECO
06/28/2019 ROOF NAILING RCAMACHO Approved
07/02/2019 EXT METAL CLIPS/EXT SHEATHING TVALENCIA Approved
07/24/2019 PLUMBING - GAS PRESSURE TEST TVALENCIA Approved
07/24/2019 RESIDENTIAL INTERMEDIATE TVALENCIA Approved
07/29/2019 MECHANICAL - INTERMEDIATE TVALENCIA Approved
07/31/2019 PLUMBING - INTERMEDIATE TVALENCIA Approved
07/31/2019 FRAMING TVALENCIA Approved
08/09/2019 SHEET ROCK NAILING DQUINN Approved
09/17/2019 GAS CLEARANCE TVALENCIA Approved
09/30/2019 PLUMBING - YARD WTR LINE/TEST DQUINN Approved
09/30/2019 ELECTRIC - UNDERGROUND DQUINN Approved
10/17/2019 ELECTRIC - FINAL DQUINN Approved
10/17/2019 OUTDOOR LIGHTING FINAL DQUINN Approved
10/17/2019 PLUMBING - PROGRESS DQUINN Approved
10/17/2019 MECHANICAL - FINAL DQUINN Approved
10/17/2019 PLUMBING - FINAL DQUINN Approved
11/18/2019 BUILDING - FINAL DQUINN Approved all documentas turned in and approved