Permit: T19CM03518
Permit Details
Apply Date:
05/17/2019
Applicant:
N/A
Description:
SFR MRSM123419 T19-M0070
Contractors:
- CIENAGA CANYON CONTRACTORS L L C
Permit Reviews
Permit Number - T19CM03518
Permit Status: C of o
Permit Description: SFR MRSM123419 T19-M0070
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/17/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 05/22/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03518
Permit Status: C of o
Permit Description: SFR MRSM123419 T19-M0070
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/17/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM03518
Permit Description: SFR MRSM123419 T19-M0070
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 05/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 06/05/2019 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | |
| 06/07/2019 | RESIDENTIAL INTERMEDIATE | MHASSAN | Approved | receptacle at Peninsula may need to be moved up if there is an overhang of the countertop. |
| 06/07/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 06/07/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | support ABS piping in middle of walls. Make sure there’s separation of the hot and cold pex or insulate hot. |
| 06/07/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE ECO |
| 06/07/2019 | ELECTRIC - CONSTRUCTION POWER | MHASSAN | Approved | OK to clear electric ECO, make sure only breaker wired up is the construction receptacle at this time. |
| 06/07/2019 | FRAMING | MHASSAN | Approved | Use correct nail plates at dryer vent |
| 06/14/2019 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | |
| 10/22/2019 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
| 10/31/2019 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
| 10/31/2019 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
| 10/31/2019 | ELECTRIC - UFER | ESTEVENS | Approved | |
| 10/31/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 11/01/2019 | PLUMBING - FINAL | TVALENCIA | Approved | |
| 11/01/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | |
| 11/01/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 11/01/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 11/07/2019 | BUILDING - FINAL | TVALENCIA | Approved |