Permit: T19CM03375
Permit Details
Apply Date:
05/10/2019
Applicant:
TLW COSNTRUCTION
Description:
STORAGE BLDG- UNITS
Permit Reviews
Permit Number - T19CM03375
Permit Status: C of o
Permit Description: STORAGE BLDG- UNITS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/25/2020 | COMMERCIAL - TI | 04/24/2020 | COMPLETED |
04/30/2020 | RESUBMITTAL - TI ALL | 06/15/2020 | COMPLETED |
05/10/2019 | PLANS OK TO SUBMIT - COMM | 05/14/2019 | COMPLETED |
05/23/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/26/2019 | COMPLETED |
06/28/2020 | RESUBMITTAL | 09/03/2020 | COMPLETED |
08/20/2020 | RESUBMITTAL | 10/09/2020 | COMPLETED |
12/11/2019 | RESUBMITTAL | 01/03/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03375
Permit Status: C of o
Permit Description: STORAGE BLDG- UNITS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/10/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM03375
Permit Description: STORAGE BLDG- UNITS
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/13/2020 | ELECTRIC - CONSTRUCTION POWER | WGALLGHER | Approved | Not a required inspection |
10/22/2020 | TEP CLEARANCE - AM | WGALLAGHER | Approved | CODE ECO |
10/22/2020 | ELECTRIC - TEMPORARY SERVICE | WGALLAGHER | Approved | |
10/22/2020 | ELECTRIC - INTERMEDIATE | WGALLAGHER | Approved | |
10/22/2020 | ELECTRIC - UNDERGROUND | WGALLAGHER | Approved | |
10/22/2020 | ELECTRIC - UFER | WGALLAGHER | Approved | |
10/22/2020 | BUILDING - PROGRESS | WGALLAGHER | Approved | |
10/22/2020 | FIREWALL/FIREBARRIER/FIRESTOP | WGALLAGHER | Approved | |
10/22/2020 | BUILDING PRE-SLAB | WGALLAGHER | Approved | |
10/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | WGALLAGHER | Approved | |
11/23/2020 | FRAMING | WGALLAGHER | Approved | |
11/23/2020 | ROOF NAILING | WGALLAGHER | Approved | |
11/23/2020 | EXT METAL CLIPS/EXT SHEATHING | WGALLAGHER | Approved | |
12/01/2020 | ELECTRIC - FINAL | WGALLAGHER | Approved | |
12/01/2020 | ELECTRIC - OUTDOOR LIGHTING | WGALLAGHER | Approved | |
12/07/2020 | CERTIFICATE OF OCCUPANCY | WGALLAGHER | Approved | Partial approval ok for TCO |
12/07/2020 | MECHANICAL - FINAL | WGALLAGHER | Approved | Partial approval need air balance report |
12/07/2020 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | |
12/07/2020 | OUTDOOR LIGHTING FINAL | WGALLAGHER | Approved | |
12/07/2020 | BUILDING - FINAL | WGALLAGHER | Approved | Partial approval ok for TCO |
12/07/2020 | ENGINEERING - FINAL | DROBERTS | Approved | PARTIAL AT THIS TIME, OK FOR TCO. FINAL NOT TO BE GIVEN TILL THE DEVELOPMENT PACKAGE HAS BEEN COMPLETED. |
10/20/2021 | FIRE - ALARM FINAL | jfordney | Approved | |
10/26/2021 | FIRE SPKLR - FINAL | jfordney | Approved | |
11/09/2021 | FIRE - FINAL | jfordney | Approved |