Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
401 N BONITA AV
Address NEW:
401 N BONITA AV
Apply Date:
05/08/2019
Applicant:
JESSEROSS
Description:
CHARTER SCHOOL
Contractors:
  • CONCORD GENERAL CONTRACTING INC

Permit Reviews

Permit Number - T19CM03306
Permit Status: C of o
Permit Description: CHARTER SCHOOL
Start Date Submittal Complete Date Status  
05/08/2019 PLANS OK TO SUBMIT - COMM 05/09/2019 COMPLETED Review Details
05/09/2019 COMMERCIAL - TI 06/10/2019 COMPLETED Review Details
07/08/2019 RESUBMITTAL 08/08/2019 COMPLETED Review Details
08/08/2019 RESUBMITTAL 08/12/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM03306
Permit Status: C of o
Permit Description: CHARTER SCHOOL
Total Outstanding Activity Conditions - 1
Date Name
05/08/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM03306
Permit Description: CHARTER SCHOOL
Total Completed Inspections - 24
Date Description Inspector Results Comments
09/16/2019 ELECTRIC - INTERMEDIATE ESTEVENS Approved
09/16/2019 FRAMING ESTEVENS Approved
09/24/2019 NPPO - FINAL BBENEDON Approved
09/24/2019 SIGN - FINAL BBENEDON Approved
09/24/2019 LANDSCAPE - FINAL BBENEDON Approved
09/24/2019 PLUMBING - INTERMEDIATE JBURGE Approved Ok to cover walls
09/24/2019 RIGHT OF WAY - FINAL DR Approved
11/12/2019 MECHANICAL - HYDRONIC PIPING DQUINN Approved Bldg B - dining room and Bldg A - all 1st floor classrooms ok to drop tiles.
11/12/2019 MECHANICAL - ABOVE CEILING DQUINN Approved Bldg B - dining room and Bldg A - all 1st floor classrooms ok to drop tiles.
11/12/2019 ELECTRIC - ABOVE CEILING DQUINN Approved Bldg B - dining room and Bldg A - all 1st floor classrooms ok to drop tiles.
11/12/2019 BUILDING ABOVE CEILING DQUINN Approved Bldg B - dining room and Bldg A - all 1st floor classrooms ok to drop tiles.
11/12/2019 ENGINEERING - FINAL BBENEDON Approved
12/11/2019 PLUMBING - ROUGH, SOIL ESTEVENS Approved APPROVED PER 1090 APPROVAL
12/11/2019 MECHANICAL - INTERMEDIATE ESTEVENS Approved APPROVED PER 1090 APPROVAL
12/11/2019 SHEET ROCK NAILING ESTEVENS Approved APPRVED PER 1090 APPROVAL
12/11/2019 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT REQUIRED
12/11/2019 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATE DISINFECTION REPORT COMPLETED
12/11/2019 PLUMBING - FINAL ESTEVENS Approved Pending water report.
12/11/2019 MECHANICAL - FINAL ESTEVENS Approved Pending air balance report
12/11/2019 ELECTRIC - FINAL ESTEVENS Approved
12/13/2019 FIRE - FINAL gsereno1 Approved All approved by state fire marshal.
12/13/2019 FIRE - ALARM FINAL gsereno1 Approved
12/13/2019 FIRE SPKLR - FINAL gsereno1 Approved
12/16/2019 BUILDING - FINAL DMERANZ1 Approved