Permit: T19CM03272
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
7510 S VIA RANCHO LA COSTA
Address NEW:
7510 S VIA RANCHO LA COSTA
Apply Date:
05/07/2019
Applicant:
MERITAGE HOMES CONSTRUCTION INC *** APA***
Description:
SFR 2302380 T19-M0053
Contractors:
- MERITAGE HOMES CONSTRUCTION INC *** APA***
Completed Inspections
Permit Status: Final
Permit Number: T19CM03272
Permit Description: SFR 2302380 T19-M0053
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/03/2019 | PLUMBING - SEWER HCS CONNECT | AKLEINSORGE | Approved | No meter installed, final approval once line is tested Ok to backfill |
| 06/03/2019 | PLUMBING - YARD WTR LINE/TEST | AKLEINSORGE | Approved | No meter installed, final approval once line is tested |
| 06/03/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | Ok to backfill |
| 06/07/2019 | ELECTRIC - UFER | AKLEINSORGE | Approved | |
| 06/07/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | Ok for concrete placement |
| 06/07/2019 | BUILDING PRE-SLAB | AKLEINSORGE | Approved | |
| 06/07/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | |
| 07/01/2019 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
| 07/01/2019 | ROOF NAILING | DQUINN | Approved | |
| 07/05/2019 | ELECTRIC - CONSTRUCTION POWER | AKLEINSORGE | Approved | Clear eco please |
| 07/08/2019 | TEP CLEARANCE - AM | AKLEINSORGE | Approved | CODE ECO RESEND |
| 08/01/2019 | RESIDENTIAL INTERMEDIATE | MHASSAN | Approved | Secure switch boxes by garage, Finish sealing penetrations between first and second floor. Repair patch in second floor decking. Secure Romex for oven. |
| 08/01/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | please provide test on shower pan |
| 08/01/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 08/01/2019 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | |
| 08/01/2019 | FRAMING | MHASSAN | Approved | |
| 08/12/2019 | SHEET ROCK NAILING | DMUNIZ | Approved | |
| 09/23/2019 | GAS CLEARANCE | DMUNIZ | Approved | |
| 10/25/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 10/25/2019 | PLUMBING - FINAL | DMUNIZ | Approved | |
| 10/25/2019 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
| 10/25/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 10/25/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 10/25/2019 | BUILDING - FINAL | DMUNIZ | Approved |