Permit: T19CM03170
Permit Details
Apply Date:
05/03/2019
Applicant:
Description:
SFR MIRA154919 T19-M0019
Permit Reviews
Permit Number - T19CM03170
Permit Status: Expired
Permit Description: SFR MIRA154919 T19-M0019
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/03/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 05/03/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03170
Permit Status: Expired
Permit Description: SFR MIRA154919 T19-M0019
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
05/03/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
05/03/2019 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
05/03/2019 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T19CM03170
Permite Description: SFR MIRA154919 T19-M0019
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/29/2019 | COT - RSEL - Electrical Underground | N/A | Canceled | {Activity date: 05/29/2019; Status: Not Applicable; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } |
11/07/2022 | RSBU - Building Final | N/A | Canceled | Inspection Canceled |
Completed Inspections
Permit Status: Expired
Permit Number: T19CM03170
Permit Description: SFR MIRA154919 T19-M0019
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/22/2019 | COT - RSPL - Yard Water Line | Passed | {Activity date: 05/22/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by CBELL1 - } ; {Activity date: 05/21/2019; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by CBELL1 - Provide minimum 100 PSI test pressure.} ; {Activity date: 05/20/2019; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Verified size, depth, and tracer installation. No test at this time; bury at own risk.} | |
05/22/2019 | COT - RSPL - Rough Soil | Passed | {Activity date: 05/22/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by CBELL1 - } ; {Activity date: 05/21/2019; Status: Not ready for Inspection; Inspector: MRAMBER; Comment: Entered by CBELL1 - Provide minimum 100 PSI test pressure.} ; {Activity date: 05/20/2019; Status: Cancelled; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Builder discovered split pipe after scheduling.} | |
05/29/2019 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 05/29/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
05/29/2019 | COT - RSBU - Preslab | Passed | {Activity date: 05/29/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
05/29/2019 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/29/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
06/17/2019 | COT - RSBU - Roof Nailing | Passed | {Activity date: 06/17/2019; Status: Approved; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - } | |
06/17/2019 | COT - RSBU - Exterior Clips/Sheathing | Passed | {Activity date: 06/17/2019; Status: Approved; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - } | |
07/16/2019 | COT - RSPL - Sewer | Passed | {Activity date: 07/16/2019; Status: Approved; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - } | |
08/13/2019 | COT - LCBU - Framing | Passed | {Activity date: 08/13/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
08/13/2019 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 08/13/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - } | |
08/13/2019 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 08/13/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Clearance SWG. OK to set meter.} | |
09/11/2019 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/11/2019; Status: Approved; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - CODE ECO} | |
09/11/2019 | COT - RSEL - Construction Power | Passed | {Activity date: 09/11/2019; Status: Approved; Inspector: MRAMBER; Comment: Entered by DMERANZ1 - ECO OK to clear} | |
10/24/2019 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/13/2019; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Maintain code required clearance at B-vents.} | |
10/24/2019 | COT - RSME - Mechanical Final | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/22/2019; Status: Denied; Inspector: JClaxton; Comment: Entered by KROBLES1 - } | |
10/24/2019 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - } | |
10/24/2019 | COT - RSPL - Plumbing Final | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/22/2019; Status: Denied; Inspector: JClaxton; Comment: Entered by KROBLES1 - } | |
10/24/2019 | RSME - Mechanical Progress | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/13/2019; Status: Correction Required; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - Maintain code required clearance at B-vents.} | |
10/24/2019 | COT - RSEL - Electrical Final | Passed | {Activity date: 10/24/2019; Status: Approved; Inspector: JCLAXTON; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/22/2019; Status: Denied; Inspector: JClaxton; Comment: Entered by KROBLES1 - Complete all electric issues in kitchen and convenience outlet at AC unit.} | |
11/04/2019 | COT - BULD - SWG Clearance | Passed | {Activity date: 11/04/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by DMERANZ1 - RESEND} ; {Activity date: 08/13/2019; Status: Approved; Inspector: RCHANDLER; Comment: Entered by DMERANZ1 - OK TO SET METER} |