Permit: T19CM02968
Permit Details
Apply Date:
04/25/2019
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Description:
SFR PEPP2518 T18--MOO53
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Permit Reviews
Permit Number - T19CM02968
Permit Status: C of o
Permit Description: SFR PEPP2518 T18--MOO53
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/25/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 04/26/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02968
Permit Status: C of o
Permit Description: SFR PEPP2518 T18--MOO53
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/25/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM02968
Permit Description: SFR PEPP2518 T18--MOO53
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2019 | PLUMBING - BACK WATER VALVE | GWEST | Approved | |
| 05/14/2019 | PLUMBING - SEWER HCS CONNECT | GWEST | Approved | |
| 05/14/2019 | PLUMBING - YARD WTR LINE/TEST | GWEST | Approved | |
| 05/14/2019 | PLUMBING - ROUGH, SOIL | GWEST | Approved | |
| 05/20/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | |
| 05/20/2019 | ELECTRIC - UFER | DQUINN | Approved | |
| 05/20/2019 | BUILDING PRE-SLAB | DQUINN | Approved | |
| 05/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 06/12/2019 | ROOF NAILING | GWEST | Approved | |
| 06/12/2019 | EXT METAL CLIPS/EXT SHEATHING | GWEST | Approved | |
| 07/02/2019 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
| 07/02/2019 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Clear eco |
| 07/08/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 07/08/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 07/08/2019 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | CLEAR GAS |
| 07/08/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 07/08/2019 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | |
| 07/08/2019 | FRAMING | DQUINN | Approved | |
| 08/07/2019 | SHEET ROCK NAILING | MRAMBER | Approved | |
| 10/09/2019 | PLUMBING - FINAL | MRAMBER | Approved | |
| 10/09/2019 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 10/09/2019 | PLUMBING - PROGRESS | MRAMBER | Approved | |
| 10/09/2019 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
| 10/09/2019 | ELECTRIC - FINAL | MRAMBER | Approved | |
| 10/09/2019 | BUILDING - FINAL | MRAMBER | Approved | |
| 10/16/2019 | GAS CLEARANCE | DQUINN | Approved | RESEND |