Permit: T19CM02933
Permit Details
Apply Date:
04/24/2019
Applicant:
N/A
Description:
E - COT WELL SITE UPGRADE AND NEW BUILDING
Contractors:
- HERMAN CONTRACTING INC
Permit Reviews
Permit Number - T19CM02933
Permit Status: Final
Permit Description: E - COT WELL SITE UPGRADE AND NEW BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/16/2019 | COMMERCIAL - NEW | 07/17/2019 | COMPLETED |
| 07/17/2019 | RESUBMITTAL | 09/12/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02933
Permit Status: Final
Permit Description: E - COT WELL SITE UPGRADE AND NEW BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/24/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02933
Permit Description: E - COT WELL SITE UPGRADE AND NEW BUILDING
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | Electrical conduit underground ok to backfill. |
| 10/17/2019 | ELECTRIC - UFER | DMUNIZ | Approved | Ground ring in slab ok for concrete encasement. |
| 10/17/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | ok for concrete placement. |
| 10/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
| 11/05/2019 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | second lift ok to grout. |
| 11/26/2019 | ROOF NAILING | DMUNIZ | Approved | Concrete roof, rebar per plan & ok for concrete placement. |
| 02/25/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
| 02/25/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 02/25/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
| 02/25/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
| 02/25/2020 | ELECTRIC - OUTDOOR LIGHTING | DMUNIZ | Approved | |
| 02/25/2020 | ELECTRIC - INTERMEDIATE | DMUNIZ | Approved | |
| 02/25/2020 | BUILDING - FINAL | DMUNIZ | Approved | |
| 02/25/2020 | ENGINEERING - FINAL | RLEDONNE | Approved |