Permit: T19CM02917
Permit Details
Apply Date:
04/24/2019
Applicant:
MATTAMY ARIZONA CONSTRUCTION L L C ** APA **
Description:
SFR F60B19 T19-M0028
Contractors:
- MATTAMY ARIZONA CONSTRUCTION L L C ** APA **
Permit Reviews
Permit Number - T19CM02917
Permit Status: Final
Permit Description: SFR F60B19 T19-M0028
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/24/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 04/24/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02917
Permit Status: Final
Permit Description: SFR F60B19 T19-M0028
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/24/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02917
Permit Description: SFR F60B19 T19-M0028
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
06/17/2019 | GAS CLEARANCE | DQUINN | Approved | |
06/17/2019 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | CLEAR GAS |
06/17/2019 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | CLEAR ECO |
06/17/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
06/17/2019 | FRAMING | DQUINN | Approved | |
07/16/2019 | SHEET ROCK NAILING | DQUINN | Approved | |
08/23/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
08/23/2019 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | |
08/23/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
08/23/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
08/23/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
08/23/2019 | ROOF NAILING | DMUNIZ | Approved | |
08/23/2019 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
08/23/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
08/23/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
09/12/2019 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO RESEND |
10/02/2019 | MECHANICAL - FINAL | DMUNIZ | Approved | |
10/02/2019 | PLUMBING - FINAL | DMUNIZ | Approved | |
10/02/2019 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
10/02/2019 | ELECTRIC - FINAL | DMUNIZ | Approved | |
10/02/2019 | BUILDING - FINAL | DMUNIZ | Approved |