Permit: T19CM02759
Permit Details
Apply Date:
04/17/2019
Applicant:
L G I HOMES AZ CONSTRUCTION
Description:
SFR IR151518 T18-M0058
Contractors:
- L G I HOMES AZ CONSTRUCTION
Permit Reviews
Permit Number - T19CM02759
Permit Status: Final
Permit Description: SFR IR151518 T18-M0058
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/17/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 04/17/2019 | COMPLETED |
06/06/2019 | REVISION - - 1ST | 06/14/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02759
Permit Status: Final
Permit Description: SFR IR151518 T18-M0058
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/17/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02759
Permit Description: SFR IR151518 T18-M0058
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/13/2019 | PLUMBING - SEWER HCS CONNECT | AKLEINSORGE | Approved | Ok to backfill |
05/13/2019 | PLUMBING - YARD WTR LINE/TEST | AKLEINSORGE | Approved | |
05/13/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | |
05/20/2019 | BUILDING PRE-SLAB | AKLEINSORGE | Approved | Ok to pour concrete |
05/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | Ok to pour concrete |
05/20/2019 | ELECTRIC - UFER | AKLEINSORGE | Approved | Ok to pour concrete |
05/20/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | Ok to pour concrete |
06/03/2019 | ROOF NAILING | AKLEINSORGE | Approved | |
06/03/2019 | EXT METAL CLIPS/EXT SHEATHING | AKLEINSORGE | Approved | |
06/18/2019 | TEP CLEARANCE - PM | AKLEINSORGE | Approved | CODE ECO |
06/18/2019 | ELECTRIC - CONSTRUCTION POWER | AKLEINSORGE | Approved | Clear eco |
06/26/2019 | GAS CLEARANCE | AKLEINSORGE | Approved | |
06/26/2019 | MECHANICAL - INTERMEDIATE | AKLEINSORGE | Approved | |
06/26/2019 | PLUMBING - GAS PRESSURE TEST | AKLEINSORGE | Approved | Clear gas please |
06/26/2019 | PLUMBING - INTERMEDIATE | AKLEINSORGE | Approved | 1. Secure toilet flanges |
06/26/2019 | RESIDENTIAL INTERMEDIATE | AKLEINSORGE | Approved | |
06/26/2019 | FRAMING | AKLEINSORGE | Approved | |
07/02/2019 | SHEET ROCK NAILING | AKLEINSORGE | Approved | |
08/09/2019 | PLUMBING - FINAL | AKLEINSORGE | Approved | |
08/09/2019 | MECHANICAL - FINAL | AKLEINSORGE | Approved | |
08/09/2019 | OUTDOOR LIGHTING FINAL | AKLEINSORGE | Approved | |
08/09/2019 | ELECTRIC - FINAL | AKLEINSORGE | Approved | |
08/09/2019 | BUILDING - FINAL | AKLEINSORGE | Approved | 1. Install PT tag on water riser 2. Need house numbers installed |