Permit: T19CM02539
Permit Details
Apply Date:
04/11/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: VACANT SHELL / WHITE BOX
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T19CM02539
Permit Status: L of c
Permit Description: TI: VACANT SHELL / WHITE BOX
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/26/2020 | REVISION - - 2ND | 02/26/2020 | ACTIVE |
04/11/2019 | COMMERCIAL - TI | 06/06/2019 | COMPLETED |
08/16/2019 | REVISION - - 1ST | 09/10/2019 | COMPLETED |
09/10/2019 | REVISION - - 1ST | 09/11/2019 | COMPLETED |
09/11/2019 | REVISION - - 1ST | 09/17/2019 | COMPLETED |
09/17/2019 | REVISION - - 1ST | 09/23/2019 | COMPLETED |
09/23/2019 | REVISION - - 1ST | 10/07/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02539
Permit Status: L of c
Permit Description: TI: VACANT SHELL / WHITE BOX
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/11/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T19CM02539
Permit Description: TI: VACANT SHELL / WHITE BOX
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/17/2019 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
02/07/2020 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
02/20/2020 | GAS CLEARANCE | DQUINN | Approved | |
02/20/2020 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Clear gas |
02/20/2020 | SHEET ROCK NAILING | DQUINN | Approved | Ok to hang and tape all walls. |
02/20/2020 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
02/20/2020 | FRAMING | DQUINN | Approved | |
02/27/2020 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | The TEP clearance code is ECO. |
02/27/2020 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | The TEP clearance code is ECO. |
02/27/2020 | ELECTRIC - TEMPORARY SERVICE | ESTEVENS | Approved | The TEP clearance code is ECO. |
02/27/2020 | TEP CLEARANCE - AM | ESTEVENS | Approved | CODE ECO |
03/31/2020 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | RVI |
03/31/2020 | BUILDING ABOVE CEILING | DUMINZ | Approved | RVI |
03/31/2020 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | RVI |
03/31/2020 | FIREWALL/FIREBARRIER/FIRESTOP | DMUNIZ | Approved | RVI |
03/31/2020 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | |
07/24/2020 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | Approved |
07/24/2020 | PLUMBING - FINAL | JBURGE | Approved | Approved |
07/24/2020 | ELECTRIC - FINAL | JBURGE | Approved | Approved |
07/24/2020 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | Approved |
07/24/2020 | ENGINEERING - FINAL | BBENEDON | Approved | Approved. |
07/28/2020 | FIRE - FINAL | CBASALDUA | Approved | |
07/28/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
07/29/2020 | BUILDING - FINAL | WGALLAGHER | Approved | Approved recommend for C/O |
07/31/2020 | CERTIFICATE OF OCCUPANCY | JG3 | Approved |