Permit: T19CM02515
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
2848 N MOUNTAIN AV BLDG#7
Address NEW:
2848 N MOUNTAIN AV BLDG#7
Apply Date:
04/10/2019
Applicant:
A F STERLING HOME BUILDERS LTD ,
Description:
APARTMENT 5PLEX18 T18-M0022
Contractors:
- A F STERLING HOME BUILDERS LTD ,
Permit Reviews
Permit Number - T19CM02515
Permit Status: C of o
Permit Description: APARTMENT 5PLEX18 T18-M0022
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/10/2019 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 04/25/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02515
Permit Status: C of o
Permit Description: APARTMENT 5PLEX18 T18-M0022
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/10/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM02515
Permit Description: APARTMENT 5PLEX18 T18-M0022
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2019 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | 1- yard water line from meter location to bldg 11/2 stub outs is okay to cover. |
| 06/04/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | APPROVED BASED ON APPROVAL OF PLUMBING ROUGH BY RCHANDLER ON 06/04/19 |
| 06/04/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 06/25/2019 | PLUMBING - PRE SLAB | ESTEVENS | Approved | |
| 06/25/2019 | ELECTRIC - UFER | ESTEVENS | Approved | |
| 06/25/2019 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | |
| 06/25/2019 | BUILDING PRE-SLAB | ESTEVENS | Approved | |
| 06/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | |
| 12/04/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 12/04/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 02/12/2020 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | |
| 02/12/2020 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
| 02/12/2020 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 02/12/2020 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | |
| 02/12/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
| 02/12/2020 | FRAMING | ESTEVENS | Approved | |
| 02/12/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 02/12/2020 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | |
| 02/19/2020 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | All units ok |
| 04/08/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
| 04/08/2020 | ELECTRIC - CABLE DROP | ESTEVENS | Approved | RVI This is for units 7101, 7102, 7103, 7104, 7105. |
| 06/18/2020 | PLUMBING - ROOF DRAINS | ESTEVENS | Approved | |
| 06/18/2020 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | |
| 06/18/2020 | BUILDING - PROGRESS | ESTEVENS | Approved | |
| 06/18/2020 | SHEET ROCK NAILING | ESTEVENS | Approved | |
| 06/18/2020 | STEM WALL/RETAINING WALL | ESTEVENS | Approved | |
| 06/19/2020 | PLUMBING - FINAL | ESTEVENS | Approved | All five are approved. |
| 06/19/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | All five are approved. |
| 06/19/2020 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | All five are approved. |
| 06/19/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | All five are approved. |
| 06/22/2020 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 06/22/2020 | FIRE - FINAL | CBASALDUA | Approved | |
| 06/22/2020 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 08/13/2020 | BUILDING - FINAL | TTREMBULAK | Approved |