Permit: T19CM02472
Permit Details
Status:
Expired
Type:
Residential Building - One or Two Family
Address:
11210 E VAIL VISTA CT
Address NEW:
11210 E VAIL VISTA CT
Apply Date:
04/09/2019
Applicant:
Kimberly York
Description:
SFR PLAN1761 T17-M0024
Outstanding Activity Conditions
Permit Number - T19CM02472
Permit Status: Expired
Permit Description: SFR PLAN1761 T17-M0024
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 04/09/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 04/09/2019 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
| 04/09/2019 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
Completed Inspections
Permit Status: Expired
Permit Number: T19CM02472
Permit Description: SFR PLAN1761 T17-M0024
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/23/2019 | COT - RSPL - Yard Water Line | Passed | {Activity date: 04/23/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by CBELL1 - } | |
| 04/23/2019 | COT - RSPL - Sewer | Passed | {Activity date: 04/23/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by CBELL1 - } | |
| 04/23/2019 | COT - RSPL - Rough Soil | Passed | {Activity date: 04/23/2019; Status: Approved; Inspector: DQUINN; Comment: Entered by CBELL1 - } | |
| 05/06/2019 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 05/06/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 05/07/2019 | COT - RSBU - Preslab | Passed | {Activity date: 05/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } ; {Activity date: 05/06/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by CBELL1 - Provide correct set of plans for inspection} | |
| 05/07/2019 | COT - RSEL - Electrical Underground | Passed | {Activity date: 05/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } ; {Activity date: 05/06/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by CBELL1 - Provide correct set of plans for inspection} | |
| 05/07/2019 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 05/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } ; {Activity date: 05/06/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by CBELL1 - Provide correct set of plans for inspection} | |
| 05/20/2019 | COT - RSBU - Roof Nailing | Passed | {Activity date: 05/20/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 05/20/2019 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 05/20/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by CBELL1 - } | |
| 06/04/2019 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 06/04/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - CODE ECO} | |
| 06/04/2019 | COT - RSEL - Construction Power | Passed | {Activity date: 06/04/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Clear TEP (ECO).} | |
| 06/07/2019 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 06/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 06/07/2019 | COT - LCBU - Framing | Passed | {Activity date: 06/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 06/07/2019 | RSME - Mechanical Progress | Passed | {Activity date: 06/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 06/07/2019 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 06/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 07/01/2019 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 07/01/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 06/28/2019; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - work incomplete upon arrival.} | |
| 07/24/2019 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 07/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 08/14/2019 | COT - BULD - SWG Clearance | Passed | {Activity date: 08/14/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/07/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 07/24/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 08/23/2019 | COT - RSME - Mechanical Final | Passed | {Activity date: 08/23/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 08/23/2019 | RSBU - Building Final | Passed | {Activity date: 08/23/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 08/23/2019 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 08/23/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } | |
| 08/23/2019 | COT - RSPL - Plumbing Final | Passed | {Activity date: 08/23/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } ; {Activity date: 07/24/2019; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - Clear Southwest Gas.} | |
| 08/23/2019 | COT - RSEL - Electrical Final | Passed | {Activity date: 08/23/2019; Status: Approved; Inspector: DMUNIZ; Comment: Entered by DMERANZ1 - } |