Permit: T19CM02229
Permit Details
Apply Date:
04/01/2019
Applicant:
SILVERADO ROOTER AND PLUMBING INC *APA*
Description:
NEW GAS LINE PIPINF TO FEED COFFEE SHOP
Contractors:
- SILVERADO ROOTER AND PLUMBING INC *APA*
Permit Reviews
Permit Number - T19CM02229
Permit Status: Final
Permit Description: NEW GAS LINE PIPINF TO FEED COFFEE SHOP
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/01/2019 | WALK THRU - COMM | 04/01/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02229
Permit Status: Final
Permit Description: NEW GAS LINE PIPINF TO FEED COFFEE SHOP
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/01/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02229
Permit Description: NEW GAS LINE PIPINF TO FEED COFFEE SHOP
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2019 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | |
| 04/03/2019 | GAS CLEARANCE | TVALENCIA | Approved | |
| 04/03/2019 | PLUMBING - FINAL | TVALENCIA | Approved |