Permit: T19CM02160
Permit Details
Apply Date:
03/27/2019
Applicant:
LENNAR ARIZONA CONSTRUCTION INC
Description:
SFR LEN5071 T17-M0022
Contractors:
- LENNAR ARIZONA CONSTRUCTION INC
Permit Reviews
Permit Number - T19CM02160
Permit Status: Final
Permit Description: SFR LEN5071 T17-M0022
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/27/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/27/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02160
Permit Status: Final
Permit Description: SFR LEN5071 T17-M0022
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/27/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02160
Permit Description: SFR LEN5071 T17-M0022
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/22/2019 | PLUMBING - SEWER HCS CONNECT | TVALENCIA | Approved | |
| 04/22/2019 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
| 04/22/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 05/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 05/02/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
| 05/02/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
| 05/02/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
| 05/17/2019 | ROOF NAILING | RCAMACHO | Approved | |
| 05/17/2019 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 06/14/2019 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
| 06/14/2019 | RESIDENTIAL INTERMEDIATE | RCAMACHO | Approved | |
| 06/14/2019 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | |
| 06/14/2019 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
| 06/14/2019 | FRAMING | RCAMACHO | Approved | |
| 06/27/2019 | SHEET ROCK NAILING | RCAMACHO | Approved | |
| 07/03/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE ECO |
| 07/03/2019 | ELECTRIC - CONSTRUCTION POWER | MHASSAN | Approved | OK to clear electric ECO |
| 07/30/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
| 08/27/2019 | GAS CLEARANCE | BSTEVENS | Approved | |
| 09/12/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 09/19/2019 | BUILDING - FINAL | ESTEVENS | Approved | approved by inspector, awaiting special inspection certificates |
| 09/19/2019 | PLUMBING - FINAL | ESTEVENS | Approved | |
| 09/19/2019 | ELECTRIC - FINAL | ESTEVENS | Approved | |
| 09/19/2019 | BUILDING - FINAL | ESTEVENS | Approved | |
| 09/19/2019 | MECHANICAL - FINAL | ESTEVENS | Approved |