Permit: T19CM02089
Permit Details
Apply Date:
03/25/2019
Applicant:
DOUCETTE HOMES INC
Description:
SFR BRCH1268 T16-M0020
Contractors:
- DOUCETTE HOMES INC
Permit Reviews
Permit Number - T19CM02089
Permit Status: Final
Permit Description: SFR BRCH1268 T16-M0020
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/25/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/25/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM02089
Permit Status: Final
Permit Description: SFR BRCH1268 T16-M0020
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/25/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM02089
Permit Description: SFR BRCH1268 T16-M0020
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/09/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
04/09/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
04/12/2019 | BUILDING PRE-SLAB | AKLEINSORGE | Approved | Ok to pour concrete |
04/12/2019 | PLUMBING - YARD WTR LINE/TEST | AKLEINSORGE | Approved | |
04/12/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | |
04/12/2019 | ELECTRIC - UFER | AKLEINSORGE | Approved | |
04/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | AKLEINSORGE | Approved | Add 2 #4 rebar at corners of entry |
05/09/2019 | ROOF NAILING | AKLEINSORGE | Approved | |
05/31/2019 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
07/11/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | Note: Provide Approved plans on site for all further inspections. |
07/11/2019 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
07/11/2019 | FRAMING | DMUNIZ | Approved | |
07/17/2019 | PLUMBING - GAS PRESSURE TEST | DMUNIZ | Approved | no gas. |
07/17/2019 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | |
08/01/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE ECO |
08/01/2019 | ELECTRIC - CONSTRUCTION POWER | MHASSAN | Approved | OK to clear electric ECO |
01/08/2020 | MECHANICAL - FINAL | DMUNIZ | Approved | |
01/08/2020 | PLUMBING - FINAL | DMUNIZ | Approved | |
01/08/2020 | PLUMBING - PROGRESS | DMUNIZ | Approved | |
01/08/2020 | OUTDOOR LIGHTING FINAL | DMUNIZ | Approved | |
01/08/2020 | ELECTRIC - FINAL | DMUNIZ | Approved | |
01/08/2020 | BUILDING - FINAL | DMUNIZ | Approved |