Permit: T19CM01948
Permit Details
Apply Date:
03/19/2019
Applicant:
N/A
Description:
RETAIL
Contractors:
- WARWICK CONSTRUCTION INC
Permit Reviews
Permit Number - T19CM01948
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/19/2019 | PLANS OK TO SUBMIT - COMM | 03/19/2019 | COMPLETED |
05/10/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/14/2019 | COMPLETED |
06/19/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 06/19/2019 | COMPLETED |
06/19/2019 | POST 3RD PARTY REVIEW | 06/21/2019 | COMPLETED |
07/26/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 08/13/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01948
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/19/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM01948
Permit Description: RETAIL
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/23/2019 | PLUMBING - SEWER HCS CONNECT | RCAMACHO | Approved | |
05/23/2019 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | |
05/24/2019 | PLUMBING - PRE SLAB | RCAMACHO | Approved | |
06/25/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
06/25/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | |
06/25/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
06/25/2019 | FRAMING | MHASSAN | Approved | |
08/15/2019 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
08/21/2019 | PLUMBING - ABOVE CEILING | TVALENCIA | Approved | |
08/21/2019 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
08/21/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
08/21/2019 | BUILDING ABOVE CEILING | TVALENCIA | Approved | |
08/23/2019 | GAS CLEARANCE | TVALENCIA | Approved | |
08/23/2019 | PLUMBING - GAS PRESSURE TEST | TVALENCIA | Approved | Clear gas meter |
08/23/2019 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | |
08/23/2019 | ELECTRIC - SERVICE RELOCATION | TVALENCIA | Approved | |
08/23/2019 | ELECTRIC - UFER | TVALENCIA | Approved | |
08/23/2019 | SHEET ROCK NAILING | TVALENCIA | Approved | |
08/23/2019 | STEM WALL/RETAINING WALL | TVALENCIA | Approved | |
08/23/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
08/27/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
08/27/2019 | PLUMBING - GAS PRESS TEST FNL | MHASSAN | Approved | OK to clear gas for new service |
08/27/2019 | ELECTRIC - FINAL | MHASSAN | Approved | |
08/27/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
09/11/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETED |
09/11/2019 | PLUMBING - FINAL | TVALENCIA | Approved | 1- Pending Water Chlorination report approval. |
09/11/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
09/13/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
09/17/2019 | FIRE - FINAL | JPEELDAVIS | Approved | |
09/17/2019 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
09/17/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
09/17/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | 1- Pending air balance report approval. |
09/18/2019 | BUILDING - FINAL | TVALENCIA | Approved | AIR BALANCE AND FIRE COMPLETE. |