Permit: T19CM01941
Permit Details
Apply Date:
03/19/2019
Applicant:
JAT HANSON
Description:
MEDICAL OFFICE
Contractors:
- G & J DEVELOPMENT INC
Permit Reviews
Permit Number - T19CM01941
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/19/2019 | COMMERCIAL - TI | 03/21/2019 | COMPLETED |
03/21/2019 | RESUBMITTAL | 03/21/2019 | COMPLETED |
09/19/2019 | REVISION - - 1ST | 09/19/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01941
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/19/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM01941
Permit Description: MEDICAL OFFICE
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/29/2019 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
06/10/2019 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
07/09/2019 | MECHANICAL - INTERMEDIATE | GWEST | Approved | |
07/09/2019 | MECHANICAL - ABOVE CEILING | GWEST | Approved | |
07/09/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | |
07/09/2019 | ELECTRIC - ABOVE CEILING | GWEST | Approved | |
07/18/2019 | BUILDING ABOVE CEILING | GWEST | Approved | |
08/15/2019 | FIRE - FINAL | Mross | Approved | -Install ceiling in IT closet -Complete instalation of ceiling tiles |
08/15/2019 | FIRE - ALARM FINAL | Mross | Approved | Correct issue with units not shutting down on devices M126 M130 |
08/15/2019 | FIRE SPKLR - FINAL | Mross | Approved | |
08/15/2019 | NPPO - FINAL | BBENEDON | Approved | |
08/15/2019 | SIGN - FINAL | BBENEDON | Approved | |
08/15/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | |
08/15/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
08/15/2019 | PLUMBING - FINAL | MRAMBER | Approved | |
08/15/2019 | ELECTRIC - FINAL | MRAMBER | Approved | |
08/15/2019 | MECHANICAL - HYDRONIC PIPING | MRAMBER | Approved | |
08/15/2019 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | |
08/16/2019 | PLUMBING - ABOVE CEILING | RCHANDLER | Approved | |
08/16/2019 | SHEET ROCK NAILING | RCHANDLER | Approved | |
08/16/2019 | FRAMING | RCHANDLER | Approved | |
08/20/2019 | RIGHT OF WAY - FINAL | MVV | Approved | No work performed in the right of way. |
09/16/2019 | BUILDING - FINAL | RCHANDLER | Approved | All work on site complete; recommend issuing C of O. |
09/16/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
09/16/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |