Permit: T19CM01918
Permit Details
Apply Date:
03/18/2019
Applicant:
FERNANDO HINOJOSA
Description:
NEW SFR & DETACHED LIVING QUARTERS
Contractors:
- APEX DEVELOPMENT
Permit Reviews
Permit Number - T19CM01918
Permit Status: Final
Permit Description: NEW SFR & DETACHED LIVING QUARTERS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/17/2020 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 01/17/2020 | COMPLETED |
01/17/2020 | RESIDENTIAL - BLDG/WWM | 01/28/2020 | COMPLETED |
03/18/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/31/2019 | COMPLETED |
04/14/2021 | REVISION - - 2ND | 04/19/2021 | COMPLETED |
06/19/2020 | REVISION - - 1ST | 06/23/2020 | COMPLETED |
06/23/2020 | REVISION - - 1ST | 07/07/2020 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01918
Permit Status: Final
Permit Description: NEW SFR & DETACHED LIVING QUARTERS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/18/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM01918
Permit Description: NEW SFR & DETACHED LIVING QUARTERS
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/08/2021 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | APPROVED |
03/12/2021 | ELECTRIC - UFER | DQUINN | Approved | APPROVED ALL OK FOR BOTH HOUSES |
03/12/2021 | BUILDING PRE-SLAB | DQUINN | Approved | APPROVED ALL OK FOR BOTH HOUSES |
03/12/2021 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | APPROVED ALL OK FOR BOTH HOUSES |
04/09/2021 | TEP CLEARANCE - PM | RELEFANTE | Approved | CODE ECO |
04/09/2021 | ELECTRIC - CONSTRUCTION POWER | RELEFANTE | Approved | AP Clear ECO |
05/06/2021 | ROOF NAILING | DQUINN | Approved | |
05/06/2021 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
06/07/2021 | MECHANICAL - INTERMEDIATE | RELEFANTE | Approved | |
06/07/2021 | PLUMBING - YARD WTR LINE/TEST | RELEFANTE | Approved | |
06/07/2021 | PLUMBING - INTERMEDIATE | RELEFANTE | Approved | |
06/07/2021 | ELECTRIC - UNDERGROUND | RELEFANTE | Approved | |
06/07/2021 | RESIDENTIAL INTERMEDIATE | RELEFANTE | Approved | |
06/07/2021 | FRAMING | RELEFANTE | Approved | |
09/29/2021 | GAS CLEARANCE | DQUINN | Approved | CODE GAS |
09/29/2021 | MECHANICAL - FINAL | DQUINN | Approved | Ap Clear gas Close permit |
09/29/2021 | PLUMBING - FINAL | DQUINN | Approved | Ap |
09/29/2021 | PLUMBING - PROGRESS | DQUINN | Approved | Ap |
09/29/2021 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
09/29/2021 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
10/04/2021 | BUILDING - FINAL | KEN | Approved | TRUSS FILED |