Permit: T19CM01530
Permit Details
Apply Date:
03/05/2019
Applicant:
MATTAMY ARIZONA CONSTRUCTION L L C ** APA **
Description:
SFR F40J18 T18-M0042
Contractors:
- MATTAMY ARIZONA CONSTRUCTION L L C ** APA **
Permit Reviews
Permit Number - T19CM01530
Permit Status: Final
Permit Description: SFR F40J18 T18-M0042
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/05/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 03/05/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM01530
Permit Status: Final
Permit Description: SFR F40J18 T18-M0042
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/05/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM01530
Permit Description: SFR F40J18 T18-M0042
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/19/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
04/19/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
04/29/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
04/29/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
04/29/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
04/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
05/28/2019 | ROOF NAILING | DQUINN | Approved | |
05/28/2019 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
07/19/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
07/19/2019 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Clear gas |
07/19/2019 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
07/19/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
07/19/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
07/19/2019 | FRAMING | DQUINN | Approved | |
08/08/2019 | SHEET ROCK NAILING | MRAMBER | Approved | |
08/16/2019 | TEP CLEARANCE - PM | DMUNIZ | Approved | CODE ECO |
08/16/2019 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Clear TEP (ECO). |
09/27/2019 | GAS CLEARANCE | BSTEVENS | Approved | RESEND |
10/11/2019 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
10/11/2019 | PLUMBING - FINAL | JCLAXTON | Approved | |
10/11/2019 | ELECTRIC - SERVICE UPGRADE | JCLAXTON | Approved | |
10/11/2019 | MECHANICAL - FINAL | JCLAXTON | Approved | |
10/11/2019 | PLUMBING - PROGRESS | JCLAXTON | Approved | |
10/11/2019 | PLUMBING - BACK WATER VALVE | JCLAXTON | Approved | |
10/11/2019 | OUTDOOR LIGHTING FINAL | JCLAXTON | Approved | |
10/11/2019 | ELECTRIC - FINAL | JCLAXTON | Approved | |
10/11/2019 | BUILDING - PROGRESS | JCLAXTON | Approved | |
11/26/2019 | BUILDING - FINAL | BSTEVENS | Approved | (rvi) |