Permit: T19CM01071
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
3710 S CALLE POLAR #02
Address NEW:
3710 S CALLE POLAR #02
Apply Date:
02/12/2019
Applicant:
POSTER, CHARLES MARCUS
Description:
APARTMENT BUILDING
Architects:
- POSTER, CHARLES MARCUS
Contractors:
- GORMAN GENERAL CONTRACTORS LLC
Permit Reviews
Permit Number - T19CM01071
Permit Status: C of o
Permit Description: APARTMENT BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/12/2019 | PLANS OK TO SUBMIT - COMM | 02/13/2019 | COMPLETED |
| 03/06/2019 | COMMERCIAL - NEW | 04/22/2019 | COMPLETED |
| 04/22/2019 | RESUBMITTAL - TI ALL | 04/24/2019 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T19CM01071
Permit Status: C of o
Permit Description: APARTMENT BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/12/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM01071
Permit Description: APARTMENT BUILDING
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/11/2019 | PLUMBING - ROUGH, SOIL | JCLAXTON | Approved | Ok to backfill, need test on separate pipe run into sewer, East side to existing sewer. |
| 10/30/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
| 10/30/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
| 10/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
| 12/11/2019 | EXT METAL CLIPS/EXT SHEATHING | DMUNIZ | Approved | |
| 12/11/2019 | ROOF NAILING | DMUNIZ | Approved | |
| 12/20/2019 | ELECTRIC - UFER | MRAMBER | Approved | Provide ground rods. |
| 12/20/2019 | BUILDING ABOVE CEILING | MRAMBER | Approved | OK to pre-rock lid. |
| 01/17/2020 | U VALUE FOR WINDOW | RCHANDLER | Approved | |
| 01/28/2020 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | |
| 01/30/2020 | PLUMBING - YARD WTR LINE/TEST | WGALLAG1 | Approved | |
| 01/31/2020 | STUCCO MESH | WGALLAG1 | Approved | |
| 02/19/2020 | PLUMBING - BACK WATER VALVE | WGALLAG1 | Approved | |
| 02/19/2020 | PLUMBING - SEWER HCS CONNECT | WGALLAG1 | Approved | |
| 02/20/2020 | FRAMING | WGALLAG1 | Approved | |
| 02/24/2020 | ELECTRIC - INTERMEDIATE | WGALLAGHER | Approved | |
| 02/24/2020 | FIREWALL/FIREBARRIER/FIRESTOP | WGALLAGHER | Approved | |
| 02/26/2020 | RESIDENTIAL INTERMEDIATE | MRAMBER | Approved | |
| 02/28/2020 | PLUMBING - INTERMEDIATE | DMUNIZ | Approved | |
| 03/06/2020 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | |
| 03/06/2020 | SHEET ROCK NAILING | DMUNIZ | Approved | |
| 05/08/2020 | ELECTRIC - PROGRESS | DMUNIZ | Approved | Approved, Sub panels complete for all 3 Units |
| 06/02/2020 | REINFORCED MASONRY PRE-GROUT | DMUNIZ | Approved | Not applicable |
| 06/02/2020 | STEM WALL/RETAINING WALL | DMUNIZ | Approved | Not applicable |
| 06/02/2020 | ELECTRIC - TEMPORARY SERVICE | DMUNIZ | Approved | Not applicable |
| 06/02/2020 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | Not applicable |
| 07/21/2020 | TEP CLEARANCE - PM | WGALLAGHER | Approved | CODE ECO/BUILD-2/ 2101, 2102, 2103 |
| 07/29/2020 | BUILDING - TEMP POWER FOR TEST | TTREMBULAK | Approved | Not applicable |
| 08/03/2020 | ELECTRIC - OUTDOOR LIGHTING | TTREMBULAK | Approved | Approved |
| 08/03/2020 | ELECTRIC - FINAL | TTREMBULAK | Approved | Approved |
| 08/03/2020 | OUTDOOR LIGHTING FINAL | TTREMBULAK | Approved | Approved |
| 08/03/2020 | PLUMBING - FINAL | TTREMBULAK | Approved | Approved |
| 08/03/2020 | MECHANICAL - FINAL | TTREMBULAK | Approved | Approved |
| 09/09/2020 | FIRE - FINAL | MRoss | Approved | |
| 09/09/2020 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 09/15/2020 | BUILDING - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 09/28/2020 | CERTIFICATE OF OCCUPANCY | CTREVIL | Approved | |
| 09/28/2020 | ENGINEERING - FINAL | CTREVIL | Approved |