Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
3710 S CALLE POLAR #01
Apply Date:
02/12/2019
Applicant:
POSTER, CHARLES MARCUS
Description:
CLUB HOUSE
Architects:
  • POSTER, CHARLES MARCUS
Contractors:
  • GORMAN GENERAL CONTRACTORS LLC

Permit Reviews

Permit Number - T19CM01062
Permit Status: C of o
Permit Description: CLUB HOUSE
Start Date Submittal Complete Date Status  
02/12/2019 PLANS OK TO SUBMIT - COMM 02/13/2019 COMPLETED Review Details
03/05/2019 COMMERCIAL - NEW 04/22/2019 COMPLETED Review Details
04/22/2019 RESUBMITTAL - TI ALL 04/24/2019 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T19CM01062
Permit Status: C of o
Permit Description: CLUB HOUSE
Total Outstanding Activity Conditions - 1
Date Name
02/12/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM01062
Permit Description: CLUB HOUSE
Total Completed Inspections - 37
Date Description Inspector Results Comments
10/10/2019 PLUMBING - ROUGH, SOIL ESTEVENS Approved
10/24/2019 BUILDING PRE-SLAB MRAMBER Approved
10/25/2019 EXCAVATION/LAYOUT REBAR & ZON MRAMBER Approved
12/11/2019 EXT METAL CLIPS/EXT SHEATHING DMUNIZ Approved
12/11/2019 ROOF NAILING DMUNIZ Approved
12/20/2019 ELECTRIC - UNDERGROUND MRAMBER Approved
12/20/2019 ELECTRIC - UFER MRAMBER Approved Provide ground rods
12/20/2019 BUILDING ABOVE CEILING MRAMBER Approved OK to drywall deck at lower roof
01/27/2020 STUCCO MESH DMUNIZ Approved
01/28/2020 ELECTRIC - ABOVE CEILING DMUNIZ Approved
01/30/2020 PLUMBING - YARD WTR LINE/TEST WGALLAG1 Approved
01/31/2020 ELECTRIC - INTERMEDIATE WGALLAG1 Approved
02/10/2020 PLUMBING - INTERMEDIATE WGALLAG1 Approved
02/10/2020 FRAMING WGALLAG1 Approved
02/19/2020 PLUMBING - SEWER HCS CONNECT WGALLAG1 Approved
02/19/2020 PLUMBING - BACK WATER VALVE WGALLAG1 Approved
06/25/2020 MECHANICAL - INTERMEDIATE WGALLAGHWER Approved Approved
06/25/2020 TEP CLEARANCE - AM WGALLAGHWER Approved CODE ECO
06/25/2020 BUILDING - PROGRESS WGALLAGHWER Approved Approved
06/25/2020 U VALUE FOR WINDOW WGALLAGHWER Approved Approved
08/18/2020 TEP CLEARANCE - PM TTREMBULAK Approved CODE ECO
08/18/2020 ELECTRIC - CONSTRUCTION POWER TTREMBULAK Approved Approved. TEP correction made. Clearance for TEP ECO connect ok to request again.
08/18/2020 ELECTRIC - PROGRESS TTREMBULAK Approved Approved
09/11/2020 FIRE - ALARM FINAL MRoss Approved
09/11/2020 FIRE SPKLR - FINAL MRoss Approved
09/17/2020 SITE - SEWER TTREMBULAK Approved Approved
09/17/2020 ELECTRIC - FINAL TTREMBULAK Approved Approved
09/17/2020 ELECTRIC - OUTDOOR LIGHTING TTREMBULAK Approved Approved
09/17/2020 ELECTRIC - TEMPORARY SERVICE TTREMBULAK Approved Not applicable
09/17/2020 STEM WALL/RETAINING WALL TTREMBULAK Approved Not applicable
09/24/2020 OUTDOOR LIGHTING FINAL TTREMBULAK Approved Approved
09/24/2020 PLUMBING - FINAL TTREMBULAK Approved Approved
10/01/2020 ENGINEERING - FINAL RLEDONNE Approved Approved.
10/07/2020 FIRE - FINAL MRoss Approved
10/13/2020 MECHANICAL - FINAL RSHERRY Approved REVIEW OF AIR BALANCE REPORT COMPLETED
10/14/2020 CERTIFICATE OF OCCUPANCY TTREMBULAK Approved Approved
10/14/2020 BUILDING - FINAL TTREMBULAK Approved Approved