Permit: T19CM00868
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
8647 E INNOVATIVE DR
Address NEW:
8647 E INNOVATIVE DR
Apply Date:
02/05/2019
Applicant:
PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Description:
SFR PEPP2518 T18--MOO53
Contractors:
- PEPPER VINER DEVELOPMENT CO II L L C ***APA***
Permit Reviews
Permit Number - T19CM00868
Permit Status: C of o
Permit Description: SFR PEPP2518 T18--MOO53
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 02/14/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00868
Permit Status: C of o
Permit Description: SFR PEPP2518 T18--MOO53
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/05/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM00868
Permit Description: SFR PEPP2518 T18--MOO53
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/05/2019 | PLUMBING - SEWER HCS CONNECT | BJONES | Approved | |
| 03/05/2019 | PLUMBING - YARD WTR LINE/TEST | BJONES | Approved | |
| 03/05/2019 | PLUMBING - ROUGH, SOIL | BJONES | Approved | |
| 03/12/2019 | ELECTRIC - UNDERGROUND | BJONES | Approved | returned to site-inspected the Slab Grade and associated inspections prior to pour. |
| 03/12/2019 | ELECTRIC - UFER | BJONES | Approved | returned to site-inspected the Slab Grade and associated inspections prior to pour. |
| 03/12/2019 | BUILDING PRE-SLAB | BJONES | Approved | returned to site-inspected the Slab Grade and associated inspections prior to pour. |
| 03/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | returned to site-inspected the Slab Grade and associated inspections prior to pour. |
| 03/12/2019 | ELECTRIC - UNDERGROUND | BJONES | Approved | No plans or permit on site Work incomplete |
| 03/12/2019 | ELECTRIC - UFER | BJONES | Approved | No plans or permit on site Work incomplete |
| 03/12/2019 | BUILDING PRE-SLAB | BJONES | Approved | No plans or permit on site Work incomplete |
| 03/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | No plans or permit on site Work incomplete |
| 04/05/2019 | ROOF NAILING | GWEST | Approved | |
| 04/05/2019 | EXT METAL CLIPS/EXT SHEATHING | GWEST | Approved | |
| 05/02/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
| 05/02/2019 | FRAMING | DQUINN | Approved | |
| 05/02/2019 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | |
| 05/02/2019 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 05/14/2019 | TEP CLEARANCE - PM | GWEST | Approved | CODE ECO |
| 05/14/2019 | ELECTRIC - CONSTRUCTION POWER | GWEST | Approved | TEP Clearance, ECO |
| 05/22/2019 | SHEET ROCK NAILING | DQUINN | Approved | |
| 07/24/2019 | GAS CLEARANCE | MRAMBER | Approved | RECONNECT |
| 07/25/2019 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 07/25/2019 | PLUMBING - FINAL | MRAMBER | Approved | |
| 07/25/2019 | PLUMBING - PROGRESS | MRAMBER | Approved | |
| 07/25/2019 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
| 07/25/2019 | ELECTRIC - FINAL | MRAMBER | Approved | |
| 07/25/2019 | BUILDING - FINAL | MRAMBER | Approved | |
| 07/26/2019 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
| 07/26/2019 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved |