Permit: T19CM00709
Permit Details
Apply Date:
01/31/2019
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
OFFICE
Architects:
- A23 STUDIOS
Contractors:
- A D REMODELING AND CONSTRUCTION INC
Permit Reviews
Permit Number - T19CM00709
Permit Status: C of o
Permit Description: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/31/2019 | COMMERCIAL - TI | 02/01/2019 | COMPLETED |
| 02/01/2019 | 3RD PARTY REVIEW - COMMERCIAL TI | 02/19/2019 | COMPLETED |
| 02/19/2019 | POST 3RD PARTY REVIEW | 03/22/2019 | COMPLETED |
| 03/22/2019 | REVISION - - 1ST | 03/27/2019 | COMPLETED |
| 03/27/2019 | REVISION - - 2ND | 03/27/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00709
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/31/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM00709
Permit Description: OFFICE
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/01/2019 | PLUMBING - PRE SLAB | RCAMACHO | Approved | |
| 03/26/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 04/26/2019 | MECHANICAL - ABOVE CEILING | MHASSAN | Approved | |
| 04/26/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 04/26/2019 | PLUMBING - ABOVE CEILING | MHASSAN | Approved | approval is for new domestic water line in ceiling only |
| 04/26/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | approval is for new domestic water line in ceiling only |
| 04/26/2019 | ELECTRIC - ABOVE CEILING | MHASSAN | Approved | |
| 04/26/2019 | BUILDING ABOVE CEILING | MHASSAN | Approved | |
| 05/15/2019 | MECHANICAL - FINAL | DQUINN | Approved | |
| 05/15/2019 | PLUMBING - FINAL | DQUINN | Approved | |
| 05/15/2019 | BUILDING - PROGRESS | DQUINN | Approved | |
| 05/15/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 05/15/2019 | FRAMING | DQUINN | Approved | |
| 05/15/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
| 06/20/2019 | FIRE - FINAL | jvincent | Approved | |
| 06/20/2019 | FIRE - ALARM FINAL | jvincent | Approved | |
| 06/20/2019 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 06/27/2019 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | |
| 06/27/2019 | BUILDING - FINAL | DQUINN | Approved |