Permit: T19CM00670
Permit Details
Apply Date:
01/30/2019
Applicant:
BERNAL VEGA RAUL ARMANDO &
Description:
NEW SFR
Permit Reviews
Permit Number - T19CM00670
Permit Status: Final
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/30/2019 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 01/30/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00670
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/30/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM00670
Permit Description: NEW SFR
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/11/2019 | PLUMBING - ROUGH, SOIL | GWEST | Approved | |
02/22/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | make sure to clean out footings before pour, due to recent rainstorm. |
02/22/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
02/26/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
03/25/2019 | ROOF NAILING | MHASSAN | Approved | shim middle bearing points at end trusses |
03/25/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | |
04/08/2019 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
04/08/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
04/08/2019 | FRAMING | DQUINN | Approved | |
04/09/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
04/09/2019 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | |
04/09/2019 | RESIDENTIAL INTERMEDIATE | DQUINN | Approved | |
05/08/2019 | TEP CLEARANCE - PM | DQUINN | Approved | CODE ECO |
05/08/2019 | ELECTRIC - CONSTRUCTION POWER | DQUINN | Approved | Clear eco |
07/10/2019 | MECHANICAL - FINAL | GWEST | Approved | |
07/10/2019 | PLUMBING - FINAL | GWEST | Approved | |
07/10/2019 | OUTDOOR LIGHTING FINAL | GWEST | Approved | |
07/10/2019 | ELECTRIC - FINAL | GWEST | Approved | |
07/10/2019 | ELECTRIC - UFER | GWEST | Approved | |
07/10/2019 | BUILDING - FINAL | GWEST | Approved |