Permit: T19CM00652
Permit Details
Apply Date:
01/30/2019
Applicant:
N/A
Description:
RETAIL STORE
Architects:
- SHELL, STEVEN COLT
Contractors:
- MW MORRISSEY CONSTRUCTION LLC
Permit Reviews
Permit Number - T19CM00652
Permit Status: C of o
Permit Description: RETAIL STORE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/30/2019 | COMMERCIAL - TI | 02/07/2019 | COMPLETED |
| 03/05/2019 | REVISION - - 1ST | 03/12/2019 | COMPLETED |
| 03/12/2019 | REVISION - - 2ND | 03/26/2019 | COMPLETED |
| 03/27/2019 | REVISION - - 3RD | 03/27/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00652
Permit Status: C of o
Permit Description: RETAIL STORE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/30/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM00652
Permit Description: RETAIL STORE
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 03/01/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
| 03/01/2019 | REINFORCED MASONRY PRE-GROUT | TVALENCIA | Approved | |
| 03/01/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
| 03/11/2019 | FRAMING | BSTEVENS | Approved | OK to cover all walls |
| 03/13/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 04/02/2019 | ELECTRIC - RECONNECT | ESTEVENS | Approved | TEP clearance code is RECN for suite #180 |
| 04/02/2019 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE RECN |
| 04/12/2019 | FIRE SPKLR - FINAL | jvincent | Approved | |
| 04/16/2019 | FIRE - ALARM FINAL | Mross | Approved | received NFPA72 ROC paperwork |
| 04/17/2019 | FIRE - FINAL | Mross | Approved | Provide suite keys to put in knox box repair emergency light in south hallway |
| 04/17/2019 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | Ok to make application for Certificate of Occupancy. |
| 04/17/2019 | MECHANICAL - FINAL | JBURGE | Approved | air balance report submitted to R. Sherry. |
| 04/17/2019 | PLUMBING - FINAL | JBURGE | Approved | bacteria test results submitted to R. Sherry. |
| 04/17/2019 | ELECTRIC - FINAL | JBURGE | Approved | |
| 04/17/2019 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | |
| 04/17/2019 | BUILDING - FINAL | JBURGE | Approved | |
| 04/17/2019 | BUILDING - PROGRESS | JBURGE | Approved | |
| 04/17/2019 | BUILDING ABOVE CEILING | JBURGE | Approved | |
| 04/17/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 04/18/2019 | MECHANICAL - HOOD SYSTEMS | JBURGE | Approved | PER 4090 |
| 04/18/2019 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | PER 4090 |
| 04/18/2019 | PLUMBING - ABOVE CEILING | JBURGE | Approved | per 3090 |