Permit: T19CM00376
Permit Details
Apply Date:
01/18/2019
Applicant:
RON WARFIELD
Description:
NEW SFR
Contractors:
- RUBICON HOMES L L C
Permit Reviews
Permit Number - T19CM00376
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/18/2019 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 01/18/2019 | COMPLETED |
| 01/18/2019 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/07/2019 | COMPLETED |
| 03/07/2019 | RESUBMITTAL | 03/11/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00376
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/18/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T19CM00376
Permit Description: NEW SFR
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/26/2019 | PLUMBING - YARD WTR LINE/TEST | GWEST | Approved | |
| 03/26/2019 | PLUMBING - ROUGH, SOIL | GWEST | Approved | |
| 04/02/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
| 04/02/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
| 04/02/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
| 04/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
| 05/01/2019 | ROOF NAILING | GWEST | Approved | |
| 05/01/2019 | EXT METAL CLIPS/EXT SHEATHING | GWEST | Approved | |
| 05/09/2019 | TEP CLEARANCE - PM | GWEST | Approved | CODE ECO |
| 05/09/2019 | ELECTRIC - CONSTRUCTION POWER | GWEST | Approved | TEP Clearance, ECO |
| 05/31/2019 | PLUMBING - GAS PRESSURE TEST | MRAMBER | Approved | |
| 05/31/2019 | FRAMING | MRAMBER | Approved | |
| 06/04/2019 | MECHANICAL - INTERMEDIATE | AKLEINSORGE | Approved | All corrections complete |
| 06/04/2019 | PLUMBING - INTERMEDIATE | AKLEINSORGE | Approved | All corrections complete |
| 06/04/2019 | PLUMBING - SEWER HCS CONNECT | AKLEINSORGE | Approved | |
| 06/04/2019 | RESIDENTIAL INTERMEDIATE | AKLEINSORGE | Approved | All corrections complete |
| 10/03/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
| 10/03/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 10/03/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 10/03/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | |
| 10/03/2019 | BUILDING - FINAL | RCHANDLER | Approved | |
| 10/15/2019 | GAS CLEARANCE | AQUIROZ | Approved | BOTH UNITS |