Permit: T19CM00358
Permit Details
Apply Date:
01/18/2019
Applicant:
D R H TUCSON CONSTRUCTION
Description:
SFR 4816MODEL T18-M0034
Contractors:
- D R H TUCSON CONSTRUCTION
Permit Reviews
Permit Number - T19CM00358
Permit Status: Final
Permit Description: SFR 4816MODEL T18-M0034
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/18/2019 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 01/18/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM00358
Permit Status: Final
Permit Description: SFR 4816MODEL T18-M0034
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/18/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM00358
Permit Description: SFR 4816MODEL T18-M0034
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/01/2019 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | |
02/01/2019 | PLUMBING - YARD WTR LINE/TEST | DMUNIZ | Approved | |
02/01/2019 | PLUMBING - ROUGH, SOIL | DMUNIZ | Approved | |
02/08/2019 | ELECTRIC - SERVICE UPGRADE | DMUNIZ | Approved | |
02/08/2019 | ELECTRIC - CONSTRUCTION POWER | DMUNIZ | Approved | CLEAR ECO |
02/08/2019 | ELECTRIC - UNDERGROUND | DMUNIZ | Approved | |
02/08/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
02/08/2019 | BUILDING PRE-SLAB | DMUNIZ | Approved | |
02/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | |
02/11/2019 | TEP CLEARANCE - AM | DMUNIZ | Approved | ECO |
02/27/2019 | ROOF NAILING | DQUINN | Approved | |
02/27/2019 | EXT METAL CLIPS/EXT SHEATHING | DQUINN | Approved | |
03/28/2019 | PLUMBING - GAS PRESSURE TEST | AKLEINSORGE | Approved | |
03/28/2019 | PLUMBING - INTERMEDIATE | AKLEINSORGE | Approved | |
04/02/2019 | RESIDENTIAL INTERMEDIATE | DMUNIZ | Approved | Mech-All corrections completed, ok to proceed |
04/02/2019 | MECHANICAL - INTERMEDIATE | DMUNIZ | Approved | All corrections completed, ok to proceed |
05/07/2019 | GAS CLEARANCE | AKLEINSORGE | Approved | |
05/07/2019 | SHEET ROCK NAILING | AKLEINSORGE | Approved | |
05/07/2019 | FRAMING | AKLEINSORGE | Approved | Should have been approved with intermediate inspections on 04/02/19 |
05/15/2019 | MECHANICAL - FINAL | AKLEINSORGE | Approved | |
05/15/2019 | PLUMBING - FINAL | AKLEINSORGE | Approved | |
05/15/2019 | OUTDOOR LIGHTING FINAL | AKLEINSORGE | Approved | |
05/15/2019 | ELECTRIC - FINAL | AKLEINSORGE | Approved | |
05/15/2019 | BUILDING - FINAL | AKLEINSORGE | Approved |