Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Final
Type:
Barricade and Excavation
Address:
40 E CONGRESS ST
Address NEW:
40 E CONGRESS ST
Apply Date:
03/16/2018
Applicant:
CANYON BUILDING AND DESIGN LLC *APA*
Description:
BORING UNDER TROLLEY TRACKS TO CONNECT TO SEWER MAIN TIE INTO TEP VAULT TEMPORARY NOISE EXEMPTION IS FOR WORK OF MARCH 18, 19 AND 20, 2018; WORK COMMENCES AT 9:00AM AND CONTINUES UNTIL THE FOLLOWING MORNING AT 7:00AM 03/21/2018-PLAN CHANGE-TEMP NOISE EXEMPT AND SUNLINK- TEMP NOISE EXEMPT-WORK DATES MARCH 25,26 & 27, 2018 AND APRIL 1, 2, 3, 2018 SUNLINK POWER DOWN FOR MARCH 25, 26, 27, 2018-ONLY START AT 11PM AND END 7AM EACH FOLLOWING DAY 4/16/18 WORK DESCRIPTION CHANGE: MILL/REPAVE ASPHALT ON CONGRESS ST (50' EAST AND WEST OF EXCAVATED AREA FOR ALL AFFECTED TRAVEL LANES) 05/02/2018-PLAN CHANGE SUNLINK APPROVED POWER DOWN FOR THE FOLLOWING DATES: MAY 6-9, MAY 13-16-MAY 20-23 MTW 11:00PM SUN 9PM

Outstanding Inspections

Permit Status: Final
Permit Number: T18RW01301
Permite Description: BORING UNDER TROLLEY TRACKS TO CONNECT TO SEWER MAIN TIE INTO TEP VAULT TEMPORARY NOISE EXEMPTION IS FOR WORK OF MARCH 18, 19 AND 20, 2018; WORK COMMENCES AT 9:00AM AND CONTINUES UNTIL THE FOLLOWING MORNING AT 7:00AM 03/21/2018-PLAN CHANGE-TEMP NOISE EXEMPT AND SUNLINK- TEMP NOISE EXEMPT-WORK DATES MARCH 25,26 & 27, 2018 AND APRIL 1, 2, 3, 2018 SUNLINK POWER DOWN FOR MARCH 25, 26, 27, 2018-ONLY START AT 11PM AND END 7AM EACH FOLLOWING DAY 4/16/18 WORK DESCRIPTION CHANGE: MILL/REPAVE ASPHALT ON CONGRESS ST (50' EAST AND WEST OF EXCAVATED AREA FOR ALL AFFECTED TRAVEL LANES) 05/02/2018-PLAN CHANGE SUNLINK APPROVED POWER DOWN FOR THE FOLLOWING DATES: MAY 6-9, MAY 13-16-MAY 20-23 MTW 11:00PM SUN 9PM
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
05/12/2018 TDOT-Routine Barricade Inspect N/A Continued Checked with site superintendent at 8:30 am to assure that Scott Ave. will be accessible for evening events. Still not ready at 11:00 am. Informed Inspector Cazares to follow up later today.

Completed Inspections

Permit Status: Final
Permit Number: T18RW01301
Permit Description: BORING UNDER TROLLEY TRACKS TO CONNECT TO SEWER MAIN TIE INTO TEP VAULT TEMPORARY NOISE EXEMPTION IS FOR WORK OF MARCH 18, 19 AND 20, 2018; WORK COMMENCES AT 9:00AM AND CONTINUES UNTIL THE FOLLOWING MORNING AT 7:00AM 03/21/2018-PLAN CHANGE-TEMP NOISE EXEMPT AND SUNLINK- TEMP NOISE EXEMPT-WORK DATES MARCH 25,26 & 27, 2018 AND APRIL 1, 2, 3, 2018 SUNLINK POWER DOWN FOR MARCH 25, 26, 27, 2018-ONLY START AT 11PM AND END 7AM EACH FOLLOWING DAY 4/16/18 WORK DESCRIPTION CHANGE: MILL/REPAVE ASPHALT ON CONGRESS ST (50' EAST AND WEST OF EXCAVATED AREA FOR ALL AFFECTED TRAVEL LANES) 05/02/2018-PLAN CHANGE SUNLINK APPROVED POWER DOWN FOR THE FOLLOWING DATES: MAY 6-9, MAY 13-16-MAY 20-23 MTW 11:00PM SUN 9PM
Total Completed Inspections - 1
Date Description Inspector Results Comments
07/03/2018 TDOT-EXCAV GENERAL INSPECTION DR Approved Paving complete. Rest of site work under T18RW02238