Permit: T18CM10081
Permit Details
Apply Date:
12/31/2018
Applicant:
CORNERSTONE CONTRACTORS INC
Description:
SFR CORN175618 T18-M0028
Contractors:
- CORNERSTONE CONTRACTORS INC
Permit Reviews
Permit Number - T18CM10081
Permit Status: Final
Permit Description: SFR CORN175618 T18-M0028
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/31/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 01/02/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM10081
Permit Status: Final
Permit Description: SFR CORN175618 T18-M0028
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/31/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM10081
Permit Description: SFR CORN175618 T18-M0028
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/04/2019 | PLUMBING - SEWER HCS CONNECT | RCHANDLER | Approved | |
| 01/04/2019 | PLUMBING - ROUGH, SOIL | RCHANDLER | Approved | |
| 01/11/2019 | ELECTRIC - UFER | GWEST | Approved | |
| 01/11/2019 | BUILDING PRE-SLAB | GWEST | Approved | |
| 01/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | GWEST | Approved | |
| 02/04/2019 | ROOF NAILING | GWEST | Approved | |
| 02/04/2019 | EXT METAL CLIPS/EXT SHEATHING | GWEST | Approved | |
| 02/21/2019 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE ECO |
| 02/21/2019 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | TEP code is EC0 |
| 03/21/2019 | PLUMBING - YARD WTR LINE/TEST | GWEST | Approved | |
| 03/21/2019 | PLUMBING - GAS PRESSURE TEST | GWEST | Approved | |
| 03/21/2019 | MECHANICAL - INTERMEDIATE | GWEST | Approved | |
| 03/21/2019 | PLUMBING - INTERMEDIATE | GWEST | Approved | |
| 03/21/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | |
| 03/21/2019 | FRAMING | GWEST | Approved | |
| 04/08/2019 | SHEET ROCK NAILING | MRAMBER | Approved | |
| 06/06/2019 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | |
| 06/06/2019 | PLUMBING - FINAL | MRAMBER | Approved | |
| 06/06/2019 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | |
| 06/06/2019 | REINFORCED MASONRY PRE-GROUT | MRAMBER | Approved | |
| 06/19/2019 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 06/19/2019 | ELECTRIC - FINAL | MRAMBER | Approved | |
| 06/19/2019 | BUILDING - FINAL | MRAMBER | Approved | |
| 06/21/2019 | GAS CLEARANCE | DMERANZA | Approved |