Permit: T18CM10026
Permit Details
Apply Date:
12/27/2018
Applicant:
WILSON ELECTRIC SERVICES CORP ** APA **
Description:
INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT SUNNYSIDE SCHOOL DISTRICT OCOTILLO SCHOOL
Contractors:
- WILSON ELECTRIC SERVICES CORP ** APA **
Permit Reviews
Permit Number - T18CM10026
Permit Status: Final
Permit Description: INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT SUNNYSIDE SCHOOL DISTRICT OCOTILLO SCHOOL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/25/2019 | REVISION - - 1ST | 04/25/2019 | COMPLETED |
12/27/2018 | WALK THRU - COMM | 01/30/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM10026
Permit Status: Final
Permit Description: INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT SUNNYSIDE SCHOOL DISTRICT OCOTILLO SCHOOL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/27/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM10026
Permit Description: INSTALL COMM. PV SYSTEM AND RELATED EQUIPMENT SUNNYSIDE SCHOOL DISTRICT OCOTILLO SCHOOL
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/21/2019 | ELECTRIC - UFER | DQUINN | Approved | Post footings for north canopies ok to pour |
03/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
05/08/2019 | FRAMING | AKLEINSORGE | Approved | 3 canopies on the north side and 1 canopy on the east side of school Reviewed field copy of special inspection report, submit report before final inspections. |
05/08/2019 | ROOF NAILING | AKLEINSORGE | Approved | 3 canopies on the north side and 1 canopy on the east side of school |
06/03/2019 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | |
06/14/2019 | ELECTRIC - SERVICE UPGRADE | MHASSAN | Approved | this is not for a service upgrade OK to clear electric DGL |
07/16/2019 | ELECTRIC - OUTDOOR LIGHTING | AKLEINSORGE | Approved | |
07/16/2019 | ELECTRIC - INTERMEDIATE | AKLEINSORGE | Approved | |
07/17/2019 | TEP CLEARANCE - PM | AKLEINSORGE | Approved | DGL/DGC |
07/17/2019 | ELECTRIC - FINAL | AKLEINSORGE | Approved | Finish installing low voltage lines, please clear dgc and dgl |
07/17/2019 | BUILDING - FINAL | AKLEINSORGE | Approved | Patch all asphalt around columns where under ground is located, finish site clean up |
07/17/2019 | OUTDOOR LIGHTING FINAL | AKLEINSORGE | Approved | |
07/17/2019 | ELECTRIC - FINAL | AKLEINSORGE | Approved | Finish installing low voltage lines |
07/17/2019 | BUILDING - FINAL | AKLEINSORGE | Approved | Patch all asphalt around columns where under ground is located, finish site clean up |