Permit: T18CM10022
Permit Details
Apply Date:
12/27/2018
Applicant:
N/A
Description:
NEW SFR
Contractors:
- PUREBUILD
Permit Reviews
Permit Number - T18CM10022
Permit Status: Final
Permit Description: NEW SFR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/22/2019 | REVISION - - 1ST | 03/22/2019 | COMPLETED |
12/27/2018 | PLANS OK TO SUBMIT - RES | 12/27/2018 | COMPLETED |
12/27/2018 | RESIDENTIAL - BLDG/ZONING/ENGINE/WWM | 03/22/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM10022
Permit Status: Final
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/27/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM10022
Permit Description: NEW SFR
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/26/2019 | PLUMBING - YARD WTR LINE/TEST | TVALENCIA | Approved | |
04/26/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
04/30/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
05/03/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
05/03/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
05/03/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | add two number five rebar on each end of wall that backs up to garage per plan. |
06/25/2019 | TEP CLEARANCE - PM | RCAMACHO | Approved | CODE ECO |
06/25/2019 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
06/25/2019 | ELECTRIC - CONSTRUCTION POWER | RCAMACHO | Approved | ECO |
07/25/2019 | ROOF NAILING | TVALENCIA | Approved | |
07/25/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
08/15/2019 | PLUMBING - GAS PRESSURE TEST | TVALENCIA | Approved | |
08/15/2019 | RESIDENTIAL INTERMEDIATE | TVALENCIA | Approved | |
08/15/2019 | FRAMING | TVALENCIA | Approved | |
12/12/2019 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
12/12/2019 | ELECTRIC - FINAL | ESTEVENS | Approved | |
12/12/2019 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
12/12/2019 | GAS CLEARANCE | ESTEVENS | Approved | |
12/12/2019 | PLUMBING - FINAL | ESTEVENS | Approved | SWG clearance is required. |
12/16/2019 | PLUMBING - INTERMEDIATE | DMERANZ1 | Approved | APPROVED BY TVALENCIA 08/15/2019 |
12/16/2019 | MECHANICAL - INTERMEDIATE | DMERANZ1 | Approved | APPROVED BY TVALENCIA 08/15/2019 |
12/16/2019 | BUILDING - FINAL | dmeranz1 | Approved | ALL DOCS TURNED IN AND APPROVED THANK YOU |
12/16/2019 | MECHANICAL - FINAL | dmeranz1 | Approved | APPROVED PER 1090 |