Permit: T18CM09948
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
3026 E KAIBAB VISTA
Address NEW:
3026 E KAIBAB VISTA
Apply Date:
12/21/2018
Applicant:
NOE GAXIOLA
Description:
ENCLOSE CARPORT&CONVERT INTO LIVING ROOM LIVING ROOM COVERT INTO BEDROOM W/ BATHROOM
Contractors:
- MATA CONSTRUCTION L L C
Permit Reviews
Permit Number - T18CM09948
Permit Status: Final
Permit Description: ENCLOSE CARPORT&CONVERT INTO LIVING ROOM LIVING ROOM COVERT INTO BEDROOM W/ BATHROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/19/2019 | REVISION - - 1ST | 02/19/2019 | COMPLETED |
| 06/05/2019 | REVISION - - 2ND | 06/05/2019 | COMPLETED |
| 12/21/2018 | RESIDENTIAL - BLDG/ZONING-WALKTHRU | 12/21/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09948
Permit Status: Final
Permit Description: ENCLOSE CARPORT&CONVERT INTO LIVING ROOM LIVING ROOM COVERT INTO BEDROOM W/ BATHROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/21/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM09948
Permit Description: ENCLOSE CARPORT&CONVERT INTO LIVING ROOM LIVING ROOM COVERT INTO BEDROOM W/ BATHROOM
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | make sure to maintain 3 inch clearance around the bottom horizontal bar |
| 05/02/2019 | PLUMBING - INTERMEDIATE | AKLEINSORGE | Approved | |
| 05/02/2019 | PLUMBING - PRE SLAB | AKLEINSORGE | Approved | Ok to pour after backfill. |
| 05/02/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | Ok to backfill |
| 05/02/2019 | EXT METAL CLIPS/EXT SHEATHING | AKLEINSORGE | Approved | |
| 05/24/2019 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
| 05/24/2019 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
| 05/24/2019 | FRAMING | RCAMACHO | Approved | |
| 06/07/2019 | TEP CLEARANCE - PM | MHASSAN | Approved | CODE INCR |
| 06/07/2019 | ELECTRIC - SERVICE UPGRADE | MHASSAN | Approved | OK to clear electric INCR |
| 08/06/2019 | MECHANICAL - FINAL | MHASSAN | Approved | |
| 08/06/2019 | PLUMBING - FINAL | MHASSAN | Approved | see notes under building final |
| 08/06/2019 | ELECTRIC - FINAL | MHASSAN | Approved | add cover plates onto open boxes. |
| 12/26/2019 | BUILDING - FINAL | WGALLAG1 | Approved |