| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/21/2018 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 12/26/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09943
Permit Status: C of o
Permit Description: SFR PEPP2518 T18--MOO53
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/21/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09943
Permit Description: SFR PEPP2518 T18--MOO53
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/23/2019 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | |
| 01/23/2019 | PLUMBING - SEWER HCS CONNECT | ESTEVENS | Approved | cancel by contractor |
| 01/23/2019 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
| 01/23/2019 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
| 01/30/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | |
| 01/30/2019 | BUILDING PRE-SLAB | TVALENCIA | Approved | |
| 01/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
| 02/21/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 02/21/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | |
| 03/14/2019 | TEP CLEARANCE - PM | TVALENCIA | Approved | CODE ECO |
| 03/14/2019 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Clear electric ECO |
| 03/14/2019 | ELECTRIC - UFER | TVALENCIA | Approved | |
| 03/27/2019 | FRAMING | RCHANDLER | Approved | |
| 03/27/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 03/27/2019 | PLUMBING - GAS PRESSURE TEST | RCHANDLER | Approved | |
| 03/27/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 03/27/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
| 03/27/2019 | FRAMING | RCHANDLER | Approved | |
| 04/16/2019 | SHEET ROCK NAILING | TVALENCIA | Approved | |
| 04/16/2019 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENCIA | Approved | |
| 06/28/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 06/28/2019 | PLUMBING - PROGRESS | RCHANDLER | Approved | |
| 06/28/2019 | PLUMBING - FINAL | RCHANDLER | Approved | |
| 06/28/2019 | MECHANICAL - FINAL | RCHANDLER | Approved | |
| 07/01/2019 | GAS CLEARANCE | ESTEVENS | Approved | |
| 07/01/2019 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | Southwest gas clearance required |
| 07/01/2019 | BUILDING - FINAL | ESTEVENS | Approved | |
| 07/01/2019 | ELECTRIC - FINAL | ESTEVENS | Approved |