Permit: T18CM09905
Permit Details
Apply Date:
12/20/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI:OFFICE
Architects:
- EGLIN, EVAN SAR
Contractors:
- G 2 CONTRACTING L L C
Permit Reviews
Permit Number - T18CM09905
Permit Status: L of c
Permit Description: TI:OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/08/2019 | COMMERCIAL - TI | 02/08/2019 | COMPLETED |
| 02/08/2019 | RESUBMITTAL | 02/20/2019 | COMPLETED |
| 02/20/2019 | RESUBMITTAL | 02/28/2019 | COMPLETED |
| 02/28/2019 | RESUBMITTAL | 02/28/2019 | COMPLETED |
| 02/28/2019 | RESUBMITTAL | 10/31/2019 | COMPLETED |
| 12/20/2018 | PLANS OK TO SUBMIT - COMM | 12/20/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09905
Permit Status: L of c
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/20/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM09905
Permit Description: TI:OFFICE
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/08/2019 | FRAMING | TVALENCIA | Approved | |
| 07/24/2019 | ELECTRIC - ABOVE CEILING | TVALENCIA | Approved | |
| 08/26/2019 | MECHANICAL - ABOVE CEILING | TVALENCIA | Approved | |
| 08/26/2019 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
| 08/26/2019 | ELECTRIC - INTERMEDIATE | TVALENCIA | Approved | |
| 08/26/2019 | BUILDING ABOVE CEILING | TVALENCIA | Approved | |
| 10/09/2019 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
| 10/09/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
| 10/09/2019 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 10/11/2019 | FIRE - FINAL | JPEELDAVIS | Approved | |
| 10/30/2019 | BUILDING - FINAL | RSHERRY | Approved | MECHANICAL AND FIRE FINALS APPROVED |
| 10/30/2019 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |