Permit: T18CM09898
Permit Details
Apply Date:
12/20/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW SHELL
Contractors:
- BARKER CONTRACTING INC **APA**
Permit Reviews
Permit Number - T18CM09898
Permit Status: L of c
Permit Description: NEW SHELL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/07/2019 | 3RD PARTY REVIEW - COMMERCIAL | 01/25/2019 | COMPLETED |
01/25/2019 | POST 3RD PARTY REVIEW | 01/30/2019 | COMPLETED |
01/30/2019 | POST 3RD PARTY REVIEW | 01/31/2019 | COMPLETED |
05/07/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 05/07/2019 | ACTIVE |
12/20/2018 | PLANS OK TO SUBMIT - COMM | 12/21/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09898
Permit Status: L of c
Permit Description: NEW SHELL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/20/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM09898
Permit Description: NEW SHELL
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/14/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
02/14/2019 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | |
02/20/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | |
03/05/2019 | ELECTRIC - UFER | MHASSAN | Approved | |
03/05/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | |
04/23/2019 | ROOF NAILING | MHASSAN | Approved | |
04/23/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | finish screwing off sheer walls at bottom track and missed areas on west wall. |
05/15/2019 | FRAMING | RCAMACHO | Approved | |
05/30/2019 | SHEET ROCK NAILING | MHASSAN | Approved | approval is for one siding of the demising wall, the TI will be responsible for the other side. |
06/03/2019 | PLUMBING - ROOF DRAINS | MHASSAN | Approved | make sure to use correct approved strapping for supporting the PVC pipes. Water test ok |
06/24/2019 | NPPO - FINAL | BBENEDON | Approved | |
06/24/2019 | MECHANICAL - FINAL | MHASSAN | Approved | shell only permit, mechanical will be run on TI permits. |
06/24/2019 | MECHANICAL - ABOVE CEILING | MHASSAN | Approved | shell only permit, mechanical will be run on TI permits. |
06/24/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | approval is for curbs and pathways only as this is a shell only permit. |
06/24/2019 | PLUMBING - FINAL | MHASSAN | Approved | approval is for plumbing into the building only as this is a shell only permit. |
06/24/2019 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | approval is for plumbing into the building only as this is a shell only permit. |
06/24/2019 | ELECTRIC - ABOVE CEILING | MHASSAN | Approved | approval is for future use conduit up to mechanical units only as this is a shell only permit. |
06/24/2019 | STUCCO MESH | MHASSAN | Approved | |
06/24/2019 | BUILDING ABOVE CEILING | MHASSAN | Approved | approval is only for water and future use conduit in the ceiling as this is a shell only permit. |
06/24/2019 | STEM WALL/RETAINING WALL | MHASSAN | Approved | |
06/24/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
06/24/2019 | RIGHT OF WAY - FINAL | Bravin | Approved | No Right of way work needed |
06/27/2019 | TEP CLEARANCE - PM | RCAMACHO | Approved | Suite 100 & house panel CODE ECO |
06/27/2019 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | ECO Suite 100 & house panel To remain locked out/tagged out |
07/11/2019 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | APPROVED PER 2090 APPROVAL |
07/11/2019 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
07/11/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
07/12/2019 | U VALUE FOR WINDOW | TVALENCIA | Approved | |
07/12/2019 | LANDSCAPE - FINAL | BBENEDON | Approved | |
07/12/2019 | SIGN - FINAL | BBENEDON | Approved | |
07/16/2019 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
07/22/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
07/24/2019 | FIRE - FINAL | gsereno1 | Approved | |
07/24/2019 | FIRE - FINAL | JPEELDAVIS | Approved | Need to lock keys in KNOX box and FDC cap |
07/24/2019 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
08/13/2019 | ZONING - FINAL | AHINES2 | Approved | Verified SF is consistent with DP16-0044 signed 7/25/19. |
09/10/2019 | REINFORCED MASONRY PRE-GROUT | TVALENCIA | Approved | |
09/10/2019 | BUILDING - FINAL | TVALENCIA | Approved | |
09/10/2019 | BUILDING - FINAL | DROBERTS | Approved |