Permit: T18CM09246
Permit Details
Apply Date:
11/23/2018
Applicant:
JESSE ESPINOZA
Description:
NEW SFR
Contractors:
- CIENAGA CANYON CONTRACTORS L L C
Permit Reviews
Permit Number - T18CM09246
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/23/2018 | PLANS OK TO SUBMIT - RES | 11/26/2018 | COMPLETED |
| 11/26/2018 | RESIDENTIAL - BLDG/WWM | 12/19/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09246
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/23/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09246
Permit Description: NEW SFR
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/06/2018 | MECHANICAL - FINAL | KEN | Approved | MANUAL J-D-S REPORT MUST BE APPROVED PRIOR TO INSPECTION |
| 12/20/2018 | PLUMBING - YARD WTR LINE/TEST | MHASSAN | Approved | |
| 12/20/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | move vent so it runs across footing not with footing |
| 12/21/2018 | EXCAVATION/LAYOUT REBAR & ZON | DMCCARTHY | Approved | work is incomplete ,not done,Ufer is not in, wants to know if I can come back later I said probably not but if you want to do call Armando and ask for same day inspection for a different fee at the end of the day. Customer not ready this morning at 9:11 AM return to site one hour later customer was gone but work was complete could not give them a carbon copy because they weren’t there they had a carbon copy of the not ready status. Added about 25 minutes to my route to serve the customer. And return twice. |
| 12/31/2018 | ROOF NAILING | BSTEVENS | Approved | |
| 12/31/2018 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | |
| 01/08/2019 | ELECTRIC - CONSTRUCTION POWER | DMCCARTHY | Approved | construction to permanent power TEC. Electric clearance temporary to permanent mounted on building at permanent location. Tucson electric power recommended using this code |
| 01/08/2019 | MECHANICAL - INTERMEDIATE | DMCCARTHY | Approved | unkink duct |
| 01/08/2019 | PLUMBING - INTERMEDIATE | DMCCARTHY | Approved | |
| 01/08/2019 | ELECTRIC - INTERMEDIATE | DMCCARTHY | Approved | at this inspection for today |
| 01/08/2019 | FRAMING | DMCCARTHY | Approved | added mid span strong back to gable wall |
| 01/09/2019 | TEP CLEARANCE - AM | DMCCARTHY | Approved | TEC |
| 04/01/2019 | PLUMBING - FINAL | MHASSAN | Approved | approved upon 3090 approval from MHASSAN |
| 04/01/2019 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | approved upon 3090 approval from MHASSAN |
| 04/01/2019 | OUTDOOR LIGHTING FINAL | MHASSAN | Approved | |
| 04/01/2019 | ELECTRIC - FINAL | MHASSAN | Approved | |
| 04/01/2019 | ELECTRIC - UNDERGROUND | MHASSAN | Approved | approved upon 2090 approval from MHASSAN |
| 04/01/2019 | ELECTRIC - UFER | MHASSAN | Approved | approved upon 2090 approval from MHASSAN |
| 04/01/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | approved upon 1090 approval from MHASSAN |
| 04/01/2019 | RESIDENTIAL INTERMEDIATE | MHASSAN | Approved | approved upon 1090 approval from MHASSAN |
| 04/30/2019 | BUILDING - FINAL | MHASSAN | Approved | 4090 COMPLETE |