Permit: T18CM08885
Permit Details
Apply Date:
11/07/2018
Applicant:
SOLON CORPORATION ***APA***
Description:
SOLAR PV
Contractors:
- SOLON CORPORATION ***APA***
Permit Reviews
Permit Number - T18CM08885
Permit Status: L of c
Permit Description: SOLAR PV
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/07/2018 | WALK THRU - COMM | 12/05/2018 | COMPLETED |
12/06/2018 | RESUBMITTAL | 12/18/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08885
Permit Status: L of c
Permit Description: SOLAR PV
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/07/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM08885
Permit Description: SOLAR PV
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/07/2019 | ELECTRIC - UFER | BJONES | Approved | |
01/07/2019 | EXCAVATION/LAYOUT REBAR & ZON | BJONES | Approved | |
01/10/2019 | ELECTRIC - UNDERGROUND | RCHANDLER | Approved | |
01/30/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
01/30/2019 | ELECTRIC - OUTDOOR LIGHTING | RCHANDLER | Approved | |
01/30/2019 | ELECTRIC - INTERMEDIATE | RCHANDLER | Approved | |
01/30/2019 | BUILDING - PROGRESS | RCHANDLER | Approved | |
01/30/2019 | FRAMING | RCHANDLER | Approved | |
01/30/2019 | ROOF NAILING | RCHANDLER | Approved | |
01/30/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | |
02/06/2019 | TEP CLEARANCE - AM | RCHANDLER | Approved | DGC |
02/06/2019 | ELECTRIC - FINAL | RCHANDLER | Approved | Recieved field evaluation for line side tap for PV interconnection. BY eti Conformity Services. Sent to records. |
02/06/2019 | BUILDING - FINAL | RCHANDLER | Approved | ALL OTHER INSPECTIONS APPROVED |
02/06/2019 | ELECTRIC - FINAL | DSC | Approved | Recieved field evaluation for line side tap for PV interconnection. BY eti Conformity Services. Sent to records. |