Permit: T18CM08818
Permit Details
Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
4960 E CALLE JABALI
Address NEW:
4960 E CALLE JABALI
Apply Date:
11/05/2018
Applicant:
REX, CATHERINE APPLEGATE
Description:
BATHROOMS ADD AND CofO
Architects:
- REX, CATHERINE APPLEGATE
Contractors:
- NEW INVISION CONSTRUCTION LLC
Permit Reviews
Permit Number - T18CM08818
Permit Status: C of o
Permit Description: BATHROOMS ADD AND CofO
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/05/2018 | COMMERCIAL - TI | 11/13/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM08818
Permit Status: C of o
Permit Description: BATHROOMS ADD AND CofO
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/05/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM08818
Permit Description: BATHROOMS ADD AND CofO
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2018 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 11/09/2018 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 11/27/2018 | PLUMBING - ROUGH, SOIL | GWEST | Approved | |
| 11/30/2018 | BUILDING PRE-SLAB | MRAMBER | Approved | |
| 11/30/2018 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | |
| 12/28/2018 | ROOF NAILING | GWEST | Approved | |
| 01/02/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 01/16/2019 | ELECTRIC - INTERMEDIATE | BJONES | Approved | |
| 01/16/2019 | FRAMING | BJONES | Approved | |
| 01/28/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | Shower pans ok. Toilet flanges to be set after tile. |
| 03/20/2019 | MECHANICAL - INTERMEDIATE | RCHANDLER | Approved | |
| 03/20/2019 | BUILDING - PROGRESS | RCHANDLER | Approved | |
| 03/20/2019 | BUILDING ABOVE CEILING | RCHANDLER | Approved | |
| 04/11/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
| 04/11/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 04/24/2019 | FIRE SPKLR - FINAL | MRoss | Approved | |
| 04/25/2019 | FIRE - FINAL | MRoss | Approved | |
| 05/02/2019 | BUILDING - FINAL | RSHERRY | Approved | |
| 05/03/2019 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | FIRE APPROVED |