Permit Details

Status:
L of c
Type:
COMMERCIAL NEW
Apply Date:
10/31/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW SHELL BLDG
Architects:
  • GARCIA DAVID V
Contractors:
  • BARKER CONTRACTING INC **APA**

Permit Reviews

Permit Number - T18CM08710
Permit Status: L of c
Permit Description: NEW SHELL BLDG
Start Date Submittal Complete Date Status  
01/25/2019 3RD PARTY REVIEW - REVISION/OTHER 01/25/2019 COMPLETED Review Details
02/21/2019 3RD PARTY REVIEW - REVISION/OTHER 02/21/2019 ACTIVE Review Details
02/21/2019 3RD PARTY REVIEW - REVISION/OTHER-2ND 03/07/2019 COMPLETED Review Details
10/31/2018 PLANS OK TO SUBMIT - COMM 10/31/2018 COMPLETED Review Details
12/04/2018 3RD PARTY REVIEW - COMMERCIAL 12/14/2018 COMPLETED Review Details
12/14/2018 POST 3RD PARTY REVIEW 01/25/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM08710
Permit Status: L of c
Permit Description: NEW SHELL BLDG
Total Outstanding Activity Conditions - 1
Date Name
10/31/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T18CM08710
Permit Description: NEW SHELL BLDG
Total Completed Inspections - 40
Date Description Inspector Results Comments
01/15/2019 PLUMBING - ROUGH, SOIL RCAMACHO Approved
01/24/2019 PLUMBING - PRE SLAB MHASSAN Approved underground plumbing will not get covered with concrete at this point because it is just a shell permit
01/24/2019 BUILDING PRE-SLAB MHASSAN Approved
01/24/2019 EXCAVATION/LAYOUT REBAR & ZON MHASSAN Approved
04/03/2019 ROOF NAILING MHASSAN Approved finish bracing between trusses
04/05/2019 PLUMBING - YARD WTR LINE/TEST MHASSAN Approved
04/05/2019 PLUMBING - ROOF DRAINS MHASSAN Approved add strap at Northwest corner
04/05/2019 ELECTRIC - UNDERGROUND MHASSAN Approved
05/14/2019 PLUMBING - INTERMEDIATE RCAMACHO Approved
05/14/2019 SHEET ROCK NAILING RCAMACHO Approved
05/14/2019 BUILDING ABOVE CEILING RCAMACHO Approved
05/14/2019 FRAMING RCAMACHO Approved
05/14/2019 EXT METAL CLIPS/EXT SHEATHING RCAMACHO Approved
05/20/2019 TEP CLEARANCE - PM MHASSAN Approved CODE ECO
05/20/2019 ELECTRIC - CABLE DROP MHASSAN Approved OK to clear electric ECO
06/11/2019 NPPO - FINAL BBENEDON Approved Landscaping installed by borderland under DEP permit
06/11/2019 SIGN - FINAL BBENEDON Approved Landscaping installed by borderland under DEP permit
06/11/2019 LANDSCAPE - FINAL BBENEDON Approved Landscaping installed by borderland under DEP permit
06/11/2019 MECHANICAL - INTERMEDIATE MHASSAN Approved
06/11/2019 MECHANICAL - ABOVE CEILING MHASSAN Approved
06/11/2019 PLUMBING - MD GAS/PRECONST MTG MHASSAN Approved
06/11/2019 PLUMBING - ABOVE CEILING MHASSAN Approved
06/11/2019 ELECTRIC - INTERMEDIATE MHASSAN Approved
06/11/2019 STEM WALL/RETAINING WALL MHASSAN Approved
06/11/2019 STUCCO MESH MHASSAN Approved
06/11/2019 PLUMBING - SEWER HCS CONNECT MHASSAN Approved
06/11/2019 U VALUE FOR WINDOW MHASSAN Approved
06/12/2019 PLUMBING - FINAL RSHERRY Approved REVIEW OF WATER DISINFECTION REPORT COMPLETED
06/17/2019 MECHANICAL - FINAL MHASSAN Approved this approval is for the shell only which consists of mechanical curbs on the roof, and a couple units have been set for future use. However nothing is hooked up and nothing is ducted at this time.
06/17/2019 OUTDOOR LIGHTING FINAL MHASSAN Approved all exterior lights are in, unable to test on timer system will check at building final.
06/17/2019 ELECTRIC - FINAL MHASSAN Approved make sure to label panels even if it’s only two circuits.
06/17/2019 RIGHT OF WAY - FINAL DR Approved
06/18/2019 ELECTRIC - OUTDOOR LIGHTING MHASSAN Approved
07/03/2019 FIRE SPKLR - FINAL JPEELDAVIS Approved Waterflow @ 35 seconds
07/10/2019 FIRE - ALARM FINAL JPEELDAVIS Approved
07/12/2019 FIRE - FINAL JPEELDAVIS Approved
07/25/2019 ENGINEERING - FINAL RLEDONNE Approved Per Brian Last note access from street to building complete.
07/25/2019 ELECTRIC - ABOVE CEILING MHASSAN Approved
07/25/2019 ELECTRIC - UFER MHASSAN Approved
07/25/2019 BUILDING - FINAL MHASSAN Approved

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW
001_A1.TIF CONSTRPLANS VIEW
002_A2.TIF CONSTRPLANS VIEW
003_A3.TIF CONSTRPLANS VIEW
004_A4.TIF CONSTRPLANS VIEW
005_A5.TIF CONSTRPLANS VIEW
006_A6.TIF CONSTRPLANS VIEW
007_A7.TIF CONSTRPLANS VIEW
008_A8.TIF CONSTRPLANS VIEW
009_A9.TIF CONSTRPLANS VIEW
010_S1.0.TIF CONSTRPLANS VIEW
011_S1.1.TIF CONSTRPLANS VIEW
012_S1.2.TIF CONSTRPLANS VIEW
013_S1.3.TIF CONSTRPLANS VIEW
006_S1.4.TIF CONSTRPLANS VIEW
014_S2.0.TIF CONSTRPLANS VIEW
015_S3.0.TIF CONSTRPLANS VIEW
016_S4.0.TIF CONSTRPLANS VIEW
017_MP1.0.TIF CONSTRPLANS VIEW
018_MP2.0.TIF CONSTRPLANS VIEW
019_ES1.0.TIF CONSTRPLANS VIEW
020_ES2.0.TIF CONSTRPLANS VIEW
021_E0.1.TIF CONSTRPLANS VIEW
022_E1.0.TIF CONSTRPLANS VIEW
023_E2.0.TIF CONSTRPLANS VIEW
024_E2.1.TIF CONSTRPLANS VIEW
025_L-1.TIF CONSTRPLANS VIEW
026_L-2.TIF CONSTRPLANS VIEW
027_L-3.TIF CONSTRPLANS VIEW
001_SHEET 1 OF 1.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW
T18CM08710 WATER REPORT.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW